Permit Details

Status:
Final
Type:
COMMERCIAL ALTERATION
Address NEW:
8080 E RESEARCH CT
Apply Date:
08/15/2019
Applicant:
TROY WHITE
Description:
TI: CREATE OFFICE SPACE INSIDE OF WAREHOUSE
Architects:
  • SWAN WAYNE E

Permit Reviews

Permit Number - T19CM05836
Permit Status: Final
Permit Description: TI: CREATE OFFICE SPACE INSIDE OF WAREHOUSE
Start Date Submittal Complete Date Status  
08/15/2019 COMMERCIAL - TI 08/20/2019 COMPLETED Review Details
08/20/2019 RESUBMITTAL 08/27/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T19CM05836
Permit Status: Final
Permit Description: TI: CREATE OFFICE SPACE INSIDE OF WAREHOUSE
Total Outstanding Activity Conditions - 1
Date Name
08/15/2019 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T19CM05836
Permit Description: TI: CREATE OFFICE SPACE INSIDE OF WAREHOUSE
Total Completed Inspections - 15
Date Description Inspector Results Comments
09/09/2019 BUILDING ABOVE CEILING BSTEVENS Approved
09/09/2019 PLUMBING - ROUGH, SOIL BSTEVENS Approved
09/09/2019 PLUMBING - INTERMEDIATE BSTEVENS Approved
09/09/2019 FRAMING BSTEVENS Approved
09/09/2019 MECHANICAL - INTERMEDIATE BSTEVENS Approved
09/09/2019 ELECTRIC - ABOVE CEILING BSTEVENS Approved
09/09/2019 ELECTRIC - INTERMEDIATE BSTEVENS Approved
10/23/2019 PLUMBING - FINAL RSHERRY Approved REVIEW OF WATER DISINFECTION REPORT COMPLETED
10/23/2019 MECHANICAL - FINAL RSHERRY Approved REVIEW OF AIR BALANCE REPORT COMPLETED
10/23/2019 CERTIFICATE OF OCCUPANCY BSTEVENS Approved PENDING APPROVAL OF AIR BALANCE AND CHLORINATION REPORTS.
10/23/2019 BUILDING - FINAL BSTEVENS Approved PENDING APPROVAL OF AIR BALANCE AND CHLORINATION REPORTS.
10/23/2019 ELECTRIC - FINAL BSTEVENS Approved
10/24/2019 FIRE - FINAL CBASALDUA Approved
10/24/2019 FIRE SPKLR - FINAL CBASALDUA Approved
10/24/2019 ENGINEERING - FINAL RLEDONNE Approved No work outside of building per approved plans.