Permit: T19CM05595
Permit Details
Status:
C of o
Type:
COMMERCIAL ADDITION
Address:
6188 E PIMA ST BLDG 3
Address NEW:
6188 E PIMA ST BLDG 3
Apply Date:
08/06/2019
Applicant:
SEAN DEMARS
Description:
NEW SCHOOL - BLDG 3
Architects:
- CARHUFF, PHILIP ANDREW
Contractors:
- CANYON BUILDING AND DESIGN LLC *APA*
Permit Reviews
Permit Number - T19CM05595
Permit Status: C of o
Permit Description: NEW SCHOOL - BLDG 3
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/06/2019 | PLANS OK TO SUBMIT - COMM | 08/12/2019 | COMPLETED |
| 08/12/2019 | COMMERCIAL - TI | 10/02/2019 | COMPLETED |
| 10/02/2019 | RESUBMITTAL - TI ALL | 11/04/2019 | COMPLETED |
| 11/04/2019 | RESUBMITTAL | 11/27/2019 | COMPLETED |
| 11/27/2019 | REVISION - - 1ST | 12/05/2019 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM05595
Permit Description: NEW SCHOOL - BLDG 3
Total Completed Inspections - 41
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/03/2019 | PLUMBING - INTERMEDIATE | RCHANDLER | Approved | Builder wanted 3040 Plumbing Yard Water line. |
| 12/19/2019 | ELECTRIC - FINAL | RCHANDLER | Approved | Work incomplete. |
| 12/19/2019 | PLUMBING - ROUGH, SOIL | RCHANDLER | Approved | |
| 12/19/2019 | ELECTRIC - UNDERGROUND | RCHANDLER | Approved | Also viewed feeders conduits to buildings 3 and 4, and ground rods at those locations. |
| 12/19/2019 | PLUMBING - YARD WTR LINE/TEST | RCHANDLER | Approved | |
| 12/20/2019 | ELECTRIC - UFER | RCHANDLER | Approved | |
| 12/20/2019 | EXCAVATION/LAYOUT REBAR & ZON | RCHANDLER | Approved | |
| 12/31/2019 | BUILDING - PROGRESS | MRAMBER | Approved | Interior footings OK |
| 01/06/2020 | STEM WALL/RETAINING WALL | MRAMBER | Approved | |
| 01/09/2020 | PLUMBING - PRE SLAB | MRAMBER | Approved | |
| 01/09/2020 | BUILDING PRE-SLAB | MRAMBER | Approved | |
| 02/26/2020 | REINFORCED MASONRY PRE-GROUT | RCHANDLER | Approved | Site walls |
| 04/10/2020 | ROOF NAILING | RCHANDLER | Approved | Inspected via email. |
| 04/23/2020 | EXT METAL CLIPS/EXT SHEATHING | WGALLAGHER | Approved | |
| 04/29/2020 | ELECTRIC - SERVICE UPGRADE | WGALLAGHER | Approved | |
| 04/29/2020 | ELECTRIC - TEMPORARY SERVICE | WGALLAGHER | Approved | |
| 05/07/2020 | PLUMBING - ROOF DRAINS | WGALLAGHER | Approved | |
| 05/07/2020 | PLUMBING - ABOVE CEILING | WGALLAGHER | Approved | |
| 05/07/2020 | FRAMING | WGALLAGHER | Approved | |
| 05/11/2020 | ELECTRIC - INTERMEDIATE | TTREMBULAK | Approved | RVI |
| 06/09/2020 | SITE - SEWER | TTREMBULAK | Approved | |
| 06/24/2020 | MECHANICAL - ABOVE CEILING | TTREMBULAK | Approved | Approved |
| 06/24/2020 | MECHANICAL - INTERMEDIATE | TTREMBULAK | Approved | Approved |
| 06/24/2020 | PLUMBING - PROGRESS | TTREMBULAK | Approved | Approved |
| 06/24/2020 | PLUMBING - GAS PRESSURE TEST | TTREMBULAK | Approved | Not applicable |
| 06/24/2020 | ELECTRIC - ABOVE CEILING | TTREMBULAK | Approved | Approved |
| 06/24/2020 | BUILDING ABOVE CEILING | TTREMBULAK | Approved | Approved |
| 07/22/2020 | MECHANICAL - PROGRESS | WGALLAGHER | Approved | Approved |
| 07/22/2020 | ELECTRIC - OUTDOOR LIGHTING | WGALLAGHER | Approved | Approved |
| 07/22/2020 | U VALUE FOR WINDOW | WGALLAGHER | Approved | Approved |
| 07/22/2020 | NPPO - FINAL | DROBERTS | Approved | IS APPROVED |
| 07/22/2020 | SIGN - FINAL | DROBERTS | Approved | IS APPROVED |
| 07/27/2020 | OUTDOOR LIGHTING FINAL | WGALLAGHER | Approved | Approved |
| 07/27/2020 | LANDSCAPE - FINAL | RLEDONNE | Approved | Approved. |
| 08/03/2020 | RIGHT OF WAY - FINAL | MVV | Approved | Acceptable. |
| 08/04/2020 | MECHANICAL - FINAL | WGALLAGHER | Approved | Approved |
| 08/05/2020 | PLUMBING - FINAL | WGALLAGHER | Approved | Approved |
| 08/06/2020 | FIRE - FINAL | MRoss | Approved | |
| 08/12/2020 | ENGINEERING - FINAL | RLEDONNE | Approved | Approved. |
| 08/14/2020 | BUILDING - FINAL | JG3 | Approved | |
| 08/14/2020 | BUILDING - FINAL | WGALLAGHER | Approved | INSPECTOR APPROVED BUILDING FINAL. PENDING MULTI SPECIAL INSPECTIONS. INSPECTOR NOTES: Approved recommended for C/O |