Inspection History Details
Inspection Status: Partial Approval
Inspection History: BUILDING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/14/2020 | BUILDING - FINAL | Partial Approval | INSPECTOR APPROVED BUILDING FINAL. PENDING MULTI SPECIAL INSPECTIONS. INSPECTOR NOTES: Approved recommended for C/O | |
| 08/14/2020 | BUILDING - FINAL | Approved | ||
| 08/12/2020 | BUILDING - FINAL | Partial Approval | REVIEW OF AIR BALANCE REPORT COMPLETED | |
| 08/06/2020 | BUILDING - FINAL | Partial Approval | See previous results dated 8/5/20 | |
| 08/05/2020 | BUILDING - FINAL | Partial Approval | Partial approval recommend this building for C/O | |
| 08/04/2020 | BUILDING - FINAL | Not ready for Inspection | Not ready | |
| 07/27/2020 | BUILDING - FINAL | Partial Approval | Partial approval Awaiting air balance in water system decontamination report recommend TCO for teachers and administrators only, please close restrooms that are not complete see 3090 Some ceiling tiles missing and elevator is not complete |