Permit: T19CM05592
Permit Details
Status:
C of o
Type:
COMMERCIAL ADDITION
Address:
6188 E PIMA ST BLDG 2
Address NEW:
6188 E PIMA ST BLDG 2
Apply Date:
08/06/2019
Applicant:
SEAN DEMARS
Description:
New Building
Architects:
- CARHUFF, PHILIP ANDREW
Contractors:
- CANYON BUILDING AND DESIGN LLC *APA*
Permit Reviews
Permit Number - T19CM05592
Permit Status: C of o
Permit Description: New Building
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/24/2019 | PLANS OK TO SUBMIT - COMM | 08/12/2019 | COMPLETED |
| 08/12/2019 | COMMERCIAL - TI | 10/15/2019 | COMPLETED |
| 11/01/2019 | RESUBMITTAL | 11/04/2019 | COMPLETED |
| 11/04/2019 | RESUBMITTAL | 11/27/2019 | COMPLETED |
| 11/27/2019 | REVISION - - 1ST | 12/05/2019 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM05592
Permit Description: New Building
Total Completed Inspections - 39
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/08/2019 | SITE - SEWER | RCHANDLER | Approved | |
| 11/08/2019 | PLUMBING - ROUGH, SOIL | RCHANDLER | Approved | |
| 11/08/2019 | TEP CLEARANCE - PM | RCHANDLER | Approved | CODE TMPP |
| 11/08/2019 | ELECTRIC - TEMPORARY SERVICE | RCHANDLER | Approved | Clearance TEP TMPP. Note: This service is pole mounted by job job trailer. |
| 11/08/2019 | ELECTRIC - UFER | RCHANDLER | Approved | |
| 11/15/2019 | ELECTRIC - UNDERGROUND | DQUINN | Approved | Electric service room conduits and feeders ok to backfill. PREVIOUSLY APPROVED REOPENED FOR REINSPECTION |
| 11/15/2019 | STEM WALL/RETAINING WALL | DQUINN | Approved | Perimeter stem ok to grout. |
| 12/02/2019 | TEP CLEARANCE - AM | RCHANDLER | Approved | CODE TMPP |
| 12/02/2019 | PLUMBING - SEWER HCS CONNECT | RCHANDLER | Approved | |
| 12/03/2019 | EXCAVATION/LAYOUT REBAR & ZON | RCHANDLER | Approved | PREVIOSULY APPROVED OPENED FOR RE-INSPECTION |
| 12/03/2019 | PLUMBING - PRE SLAB | RCHANDLER | Approved | |
| 12/03/2019 | BUILDING PRE-SLAB | RCHANDLER | Approved | |
| 12/05/2019 | BUILDING - PROGRESS | MRAMBER | Approved | Building B, Third lift OK column line CD south and south wall CMU OK |
| 12/13/2019 | PLUMBING - PROGRESS | RCHANDLER | Approved | Water line East side of building six; no test, bury at own risk. |
| 12/19/2019 | PLUMBING - YARD WTR LINE/TEST | RCHANDLER | Approved | |
| 12/27/2019 | REINFORCED MASONRY PRE-GROUT | MRAMBER | Approved | Top out OK pending special inspection report. |
| 03/10/2020 | PLUMBING - ROOF DRAINS | RCHANDLER | Approved | |
| 03/19/2020 | PLUMBING - INTERMEDIATE | RCHANDLER | Approved | |
| 04/08/2020 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | RVI |
| 04/08/2020 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | RVI |
| 04/10/2020 | ROOF NAILING | RCHANDLER | Approved | Inspected via email. |
| 05/08/2020 | MECHANICAL - ABOVE CEILING | TTREMBULAK | Approved | RVI |
| 05/08/2020 | PLUMBING - ABOVE CEILING | TTREMBULAK | Approved | RVI |
| 05/08/2020 | ELECTRIC - ABOVE CEILING | TTREMBULAK | Approved | RVI |
| 05/08/2020 | BUILDING ABOVE CEILING | TTREMBULAK | Approved | RVI |
| 05/08/2020 | EXT METAL CLIPS/EXT SHEATHING | TTREMBULAK | Approved | RVI |
| 07/17/2020 | MECHANICAL - PROGRESS | TTREMBULAK | Approved | Approved |
| 07/17/2020 | MECHANICAL - FINAL | TTREMBULAK | Approved | Approved |
| 07/17/2020 | ELECTRIC - FINAL | TTREMBULAK | Approved | Approved |
| 07/17/2020 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
| 07/22/2020 | ELECTRIC - OUTDOOR LIGHTING | WGALLAGHER | Approved | Approved |
| 07/22/2020 | ELECTRIC - SERVICE UPGRADE | WGALLAGHER | Approved | Not a required inspection |
| 07/22/2020 | U VALUE FOR WINDOW | WGALLAGHER | Approved | Approved |
| 07/27/2020 | OUTDOOR LIGHTING FINAL | WGALLAGHER | Approved | Approved |
| 08/05/2020 | PLUMBING - FINAL | WGALLAGHER | Approved | Approved |
| 08/11/2020 | FIRE - FINAL | MRoss | Approved | |
| 08/12/2020 | ENGINEERING - FINAL | RLEDONNE | Approved | Approved. |
| 08/14/2020 | BUILDING - FINAL | JG3 | Approved | |
| 08/14/2020 | FRAMING | WGALLAGHER | Approved | INSPECTOR APPROVED BUILDING FINAL. PENDING MULIT SPECIAL INSPECTIONS. INSPECTOR NOTES: Approved recommended for C/O |