Permit Details

Status:
C of o
Type:
COMMERCIAL ADDITION
Address NEW:
6188 E PIMA ST BLDG 2
Apply Date:
08/06/2019
Applicant:
SEAN DEMARS
Description:
New Building
Architects:
  • CARHUFF, PHILIP ANDREW
Contractors:
  • CANYON BUILDING AND DESIGN LLC *APA*

Permit Reviews

Permit Number - T19CM05592
Permit Status: C of o
Permit Description: New Building
Start Date Submittal Complete Date Status  
07/24/2019 PLANS OK TO SUBMIT - COMM 08/12/2019 COMPLETED Review Details
08/12/2019 COMMERCIAL - TI 10/15/2019 COMPLETED Review Details
11/01/2019 RESUBMITTAL 11/04/2019 COMPLETED Review Details
11/04/2019 RESUBMITTAL 11/27/2019 COMPLETED Review Details
11/27/2019 REVISION - - 1ST 12/05/2019 COMPLETED Review Details

Completed Inspections

Permit Status: C of o
Permit Number: T19CM05592
Permit Description: New Building
Total Completed Inspections - 39
Date Description Inspector Results Comments
11/08/2019 SITE - SEWER RCHANDLER Approved
11/08/2019 PLUMBING - ROUGH, SOIL RCHANDLER Approved
11/08/2019 TEP CLEARANCE - PM RCHANDLER Approved CODE TMPP
11/08/2019 ELECTRIC - TEMPORARY SERVICE RCHANDLER Approved Clearance TEP TMPP. Note: This service is pole mounted by job job trailer.
11/08/2019 ELECTRIC - UFER RCHANDLER Approved
11/15/2019 ELECTRIC - UNDERGROUND DQUINN Approved Electric service room conduits and feeders ok to backfill.
PREVIOUSLY APPROVED REOPENED FOR REINSPECTION
11/15/2019 STEM WALL/RETAINING WALL DQUINN Approved Perimeter stem ok to grout.
12/02/2019 TEP CLEARANCE - AM RCHANDLER Approved CODE TMPP
12/02/2019 PLUMBING - SEWER HCS CONNECT RCHANDLER Approved
12/03/2019 EXCAVATION/LAYOUT REBAR & ZON RCHANDLER Approved PREVIOSULY APPROVED OPENED FOR RE-INSPECTION
12/03/2019 PLUMBING - PRE SLAB RCHANDLER Approved
12/03/2019 BUILDING PRE-SLAB RCHANDLER Approved
12/05/2019 BUILDING - PROGRESS MRAMBER Approved Building B, Third lift OK column line CD south and south wall CMU OK
12/13/2019 PLUMBING - PROGRESS RCHANDLER Approved Water line East side of building six; no test, bury at own risk.
12/19/2019 PLUMBING - YARD WTR LINE/TEST RCHANDLER Approved
12/27/2019 REINFORCED MASONRY PRE-GROUT MRAMBER Approved Top out OK pending special inspection report.
03/10/2020 PLUMBING - ROOF DRAINS RCHANDLER Approved
03/19/2020 PLUMBING - INTERMEDIATE RCHANDLER Approved
04/08/2020 MECHANICAL - INTERMEDIATE RCHANDLER Approved RVI
04/08/2020 ELECTRIC - INTERMEDIATE RCHANDLER Approved RVI
04/10/2020 ROOF NAILING RCHANDLER Approved Inspected via email.
05/08/2020 MECHANICAL - ABOVE CEILING TTREMBULAK Approved RVI
05/08/2020 PLUMBING - ABOVE CEILING TTREMBULAK Approved RVI
05/08/2020 ELECTRIC - ABOVE CEILING TTREMBULAK Approved RVI
05/08/2020 BUILDING ABOVE CEILING TTREMBULAK Approved RVI
05/08/2020 EXT METAL CLIPS/EXT SHEATHING TTREMBULAK Approved RVI
07/17/2020 MECHANICAL - PROGRESS TTREMBULAK Approved Approved
07/17/2020 MECHANICAL - FINAL TTREMBULAK Approved Approved
07/17/2020 ELECTRIC - FINAL TTREMBULAK Approved Approved
07/17/2020 MECHANICAL - FINAL RSHERRY Approved REVIEW OF AIR BALANCE REPORT COMPLETED
07/22/2020 ELECTRIC - OUTDOOR LIGHTING WGALLAGHER Approved Approved
07/22/2020 ELECTRIC - SERVICE UPGRADE WGALLAGHER Approved Not a required inspection
07/22/2020 U VALUE FOR WINDOW WGALLAGHER Approved Approved
07/27/2020 OUTDOOR LIGHTING FINAL WGALLAGHER Approved Approved
08/05/2020 PLUMBING - FINAL WGALLAGHER Approved Approved
08/11/2020 FIRE - FINAL MRoss Approved
08/12/2020 ENGINEERING - FINAL RLEDONNE Approved Approved.
08/14/2020 BUILDING - FINAL JG3 Approved
08/14/2020 FRAMING WGALLAGHER Approved INSPECTOR APPROVED BUILDING FINAL. PENDING MULIT SPECIAL INSPECTIONS. INSPECTOR NOTES: Approved recommended for C/O

Documents

File Name Document Type  
T19CM05592 AIR BALANCE.PDF DOCUMENTS VIEW
T19CM05592 WATER REPORT.PDF DOCUMENTS VIEW
T19CM05592 - COFO.PDF CERT OF OCC VIEW
None DOCUMENTS VIEW