Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 07/22/2020 |
BUILDING - PROGRESS |
|
Approved |
Approved |
| 03/25/2020 |
BUILDING - PROGRESS |
|
Cancelled |
CA per phone call with customer. |
| 03/11/2020 |
BUILDING - PROGRESS |
|
Not ready for Inspection |
Work incomplete. |
| 03/09/2020 |
BUILDING - PROGRESS |
|
Partial Approval |
West side walls and two ramps at building 2. |
| 02/25/2020 |
BUILDING - PROGRESS |
|
Partial Approval |
Pregrout for site retaining/Restraining walls on South side. |
| 02/24/2020 |
BUILDING - PROGRESS |
|
Partial Approval |
Top out for retaining/restraint walls on West side of building. |
| 02/10/2020 |
BUILDING - PROGRESS |
|
Not ready for Inspection |
Work incomplete. |
| 12/05/2019 |
BUILDING - PROGRESS |
|
Partial Approval |
Building B, Third lift OK column line CD south and south wall CMU OK |
| 11/29/2019 |
BUILDING - PROGRESS |
|
Not ready for Inspection |
Not complete. |