Permit: T19CM05408
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
9300 E VALENCIA RD #18
Address NEW:
9300 E VALENCIA RD #18
Apply Date:
07/30/2019
Applicant:
N/A
Description:
NEW MAINTENANCE BUILDING
Architects:
- EGLIN, EVAN SAR
Contractors:
- HSL CONSTRUCTION SVCS LLC
Permit Reviews
Permit Number - T19CM05408
Permit Status: C of o
Permit Description: NEW MAINTENANCE BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/10/2020 | 3RD PARTY REVIEW - REVISION/OTHER | 01/10/2020 | COMPLETED |
| 07/30/2019 | PLANS OK TO SUBMIT - COMM | 09/16/2019 | COMPLETED |
| 09/16/2019 | 3RD PARTY REVIEW - COMMERCIAL | 09/16/2019 | COMPLETED |
| 09/16/2019 | POST 3RD PARTY REVIEW | 10/29/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM05408
Permit Status: C of o
Permit Description: NEW MAINTENANCE BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/30/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM05408
Permit Description: NEW MAINTENANCE BUILDING
Total Completed Inspections - 39
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/15/2020 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | |
| 03/11/2020 | STUCCO MESH | MRAMBER | Approved | |
| 04/17/2020 | ELECTRIC - UFER | TTREMBULAK | Approved | RVI |
| 04/17/2020 | EXCAVATION/LAYOUT REBAR & ZON | TTREMBULAK | Approved | RVI |
| 04/23/2020 | BUILDING PRE-SLAB | TTREMBULAK | Approved | RVI |
| 05/14/2020 | FRAMING | WGALLAGHER | Approved | |
| 05/14/2020 | ROOF NAILING | WGALLAGHER | Approved | |
| 05/14/2020 | EXT METAL CLIPS/EXT SHEATHING | WGALLAGHER | Approved | |
| 06/09/2020 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | |
| 06/09/2020 | PLUMBING - PRE SLAB | DMUNIZ | Approved | |
| 07/02/2020 | BUILDING ABOVE CEILING | DMUNIZ | Approved | Approved |
| 07/02/2020 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 07/02/2020 | PLUMBING - ABOVE CEILING | DMUNIZ | Approved | Approved |
| 07/02/2020 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 07/02/2020 | ELECTRIC - ABOVE CEILING | DMUNIZ | Approved | Approved |
| 07/02/2020 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 07/02/2020 | U VALUE FOR WINDOW | DMUNIZ | Approved | Approved |
| 07/02/2020 | MECHANICAL - ABOVE CEILING | DMUNIZ | Approved | Approved |
| 11/20/2020 | TEP CLEARANCE - PM | WGALLAGHER | Approved | CODE ECO |
| 11/20/2020 | ELECTRIC - CABLE DROP | WGALLAGHER | Approved | Approved ok for clearance eco |
| 06/30/2021 | FIRE - FINAL | wmotto1 | Approved | |
| 06/30/2021 | FIRE - ALARM FINAL | wmotto1 | Approved | |
| 06/30/2021 | FIRE SPKLR - FINAL | wmotto1 | Approved | |
| 06/30/2021 | SITE - SEWER | WGALLAGHER | Approved | |
| 06/30/2021 | PLUMBING - MD GAS/PRECONST MTG | WGALLAGHER | Approved | |
| 06/30/2021 | ELECTRIC - SERVICE UPGRADE | WGALLAGHER | Approved | APPROVED NO CLEARANCES NEEDED |
| 06/30/2021 | ELECTRIC - UNDERGROUND | WGALLAGHER | Approved | |
| 06/30/2021 | SHEET ROCK NAILING | WGALLAGHER | Approved | |
| 07/01/2021 | MECHANICAL - FINAL | DQUINN | Approved | |
| 07/01/2021 | PLUMBING - FINAL | DQUINN | Approved | |
| 07/01/2021 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | |
| 07/01/2021 | ELECTRIC - FINAL | DQUINN | Approved | |
| 07/01/2021 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | |
| 07/01/2021 | BUILDING - FINAL | DQUINN | Approved | |
| 08/27/2021 | ENGINEERING - FINAL | DROBERTS | Approved | APPROVED PENDING ALL OTHER INSPECTIONS |
| 09/01/2021 | RIGHT OF WAY - FINAL | BMONG | Approved | jack K was PIA inspector he says ROW meets spec |
| 09/10/2021 | NPPO - FINAL | MHERNANDEZ | Approved | APPROVED |
| 09/10/2021 | SIGN - FINAL | MHERNANDEZ | Approved | APPROVED |
| 09/10/2021 | LANDSCAPE - FINAL | MHERNANDEZ | Approved | APPROVED |