Permit: T19CM05219
Permit Details
Status:
Final
Type:
SINGLE FAMILY NEW
Address:
200 S AVENIDA DEL PALO FIERO
Address NEW:
200 S AVENIDA DEL PALO FIERO
Apply Date:
07/23/2019
Applicant:
N/A
Description:
NEW SFR
Contractors:
- GIPSON CORWIN HOMES L L C
Outstanding Activity Conditions
Permit Number - T19CM05219
Permit Status: Final
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/23/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM05219
Permit Description: NEW SFR
Total Completed Inspections - 35
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/29/2019 | PLUMBING - SEWER HCS CONNECT | BSTEVENS | Approved | (RVI) |
| 10/01/2019 | ELECTRIC - UFER | BSTEVENS | Approved | (RVI) |
| 10/01/2019 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | (RVI) |
| 10/15/2019 | STEM WALL/RETAINING WALL | BSTEVENS | Approved | (RVI) |
| 10/21/2019 | PLUMBING - ROUGH, SOIL | BSTEVENS | Approved | (rvi) Reinspect approved |
| 10/21/2019 | PLUMBING - ROUGH, SOIL | BSTEVENS | Approved | (RVI) NO TEST ON DWV SYSTEM |
| 11/12/2019 | TEP CLEARANCE - PM | BSTEVENS | Approved | CODE ECO |
| 12/12/2019 | REINFORCED MASONRY PRE-GROUT | BSTEVENS | Approved | RVI - OK TO GROUT TO 14' |
| 03/27/2020 | ELECTRIC - UNDERGROUND | DQUINN | Approved | |
| 03/27/2020 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | |
| 06/01/2020 | ROOF NAILING | TVALENCIA | Approved | |
| 06/29/2020 | EXT METAL CLIPS/EXT SHEATHING | TVALENICA | Approved | approved |
| 08/21/2020 | GAS CLEARANCE | WGALLAGHER | Approved | CODE |
| 08/21/2020 | PLUMBING - GAS PRESSURE TEST | WGALLAGHER | Approved | Approved ok for clearance |
| 08/21/2020 | PLUMBING - YARD WTR LINE/TEST | WGALLAGHER | Approved | Partial approval need ball valve at service entrance |
| 08/21/2020 | PLUMBING - INTERMEDIATE | WGALLAGHER | Approved | Approved |
| 08/21/2020 | ELECTRIC - CONSTRUCTION POWER | WGALLAGHER | Approved | Not a required inspection |
| 08/21/2020 | RESIDENTIAL INTERMEDIATE | WGALLAGHER | Approved | Approved need 2 whole strap on gas line inside service entrance |
| 08/21/2020 | FRAMING | WGALLAGHER | Approved | Approved |
| 08/21/2020 | MECHANICAL - INTERMEDIATE | WGALLAGHER | Approved | Approved |
| 08/21/2020 | PLUMBING - GAS PRESSURE TEST | WGALLAGHER | Approved | Approved |
| 08/21/2020 | PLUMBING - YARD WTR LINE/TEST | WGALLAGHER | Approved | Partial approval need ball valve at service entrance |
| 08/21/2020 | PLUMBING - INTERMEDIATE | WGALLAGHER | Approved | Approved |
| 08/21/2020 | ELECTRIC - CONSTRUCTION POWER | WGALLAGHER | Approved | Not a required inspection |
| 08/21/2020 | RESIDENTIAL INTERMEDIATE | WGALLAGHER | Approved | Approved need 2 whole strap on gas line inside service entrance |
| 08/21/2020 | FRAMING | WGALLAGHER | Approved | Approved |
| 09/04/2020 | FIREWALL/FIREBARRIER/FIRESTOP | JBURGE | Approved | Approved. |
| 02/17/2021 | BUILDING PRE-SLAB | JBURGE | Approved | 1090 |
| 02/17/2021 | ELECTRIC - FINAL | JBURGE | Approved | Approved |
| 02/17/2021 | PLUMBING - PROGRESS | JBURGE | Approved | Approved |
| 02/17/2021 | PLUMBING - FINAL | JBURGE | Approved | Approved |
| 02/17/2021 | MECHANICAL - FINAL | JBURGE | Approved | Approved |
| 03/30/2021 | FIRE - FINAL | CBASALDUA | Approved | |
| 03/30/2021 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 10/18/2022 | BUILDING - FINAL | CTREVIL | Approved |