Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/28/2020 | REINFORCED MASONRY PRE-GROUT | Approved | RVI OK TO TOP OF WALLS |
|
| 02/21/2020 | REINFORCED MASONRY PRE-GROUT | Partial Approval | RVI SECOND TO LAST LIFT (20 TO 24') |
|
| 01/28/2020 | REINFORCED MASONRY PRE-GROUT | Partial Approval | RVI OK TO GROUT 5TH LIFT (20'+ OR -) |
|
| 01/10/2020 | REINFORCED MASONRY PRE-GROUT | Partial Approval | RVI - OK TO GROUT TO 16' (4TH LIFT) | |
| 12/12/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | RVI - OK TO GROUT TO 14' | |
| 11/21/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | (RVI) SECOND LIFT OK TO GROUT | |
| 10/30/2019 | REINFORCED MASONRY PRE-GROUT | Partial Approval | (RVI) FIRST LIFT (4') OK TO GROUT. |