Permit: T19CM05199
Permit Details
Apply Date:
07/23/2019
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW VETERINARY FACILITY
Architects:
- A23 STUDIOS
Contractors:
- CALDWELL CONSTRUCTION LLC
Permit Reviews
Permit Number - T19CM05199
Permit Status: C of o
Permit Description: NEW VETERINARY FACILITY
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/23/2019 | PLANS OK TO SUBMIT - COMM | 07/23/2019 | COMPLETED |
| 07/25/2019 | 3RD PARTY REVIEW - COMMERCIAL | 10/15/2019 | COMPLETED |
| 10/15/2019 | POST 3RD PARTY REVIEW | 10/23/2019 | COMPLETED |
| 10/23/2019 | POST 3RD PARTY REVIEW | 10/29/2019 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T19CM05199
Permit Status: C of o
Permit Description: NEW VETERINARY FACILITY
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/23/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM05199
Permit Description: NEW VETERINARY FACILITY
Total Completed Inspections - 49
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/21/2020 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | |
| 02/19/2020 | PLUMBING - PRE SLAB | DMUNIZ | Approved | Plumbing wrapped and ok for concrete. |
| 04/09/2020 | SITE - SEWER | WGALLAGHER | Approved | |
| 04/09/2020 | PLUMBING - SEWER HCS CONNECT | WGALLAGHER | Approved | |
| 05/06/2020 | ELECTRIC - UNDERGROUND | TTREMBULAK | Approved | RVI |
| 05/15/2020 | ROOF NAILING | WGALLAGHER | Approved | |
| 05/15/2020 | EXT METAL CLIPS/EXT SHEATHING | WGALLAGHER | Approved | |
| 05/21/2020 | EXCAVATION/LAYOUT REBAR & ZON | WGALLAGHER | Approved | North, west, and south site foundation wall footers ok for concrete placement |
| 05/21/2020 | U VALUE FOR WINDOW | WGALLAGHER | Approved | |
| 06/02/2020 | PLUMBING - GAS PRESSURE TEST | WGALLAGHER | Approved | ok for clearance swg |
| 06/02/2020 | PLUMBING - ROOF DRAINS | WGALLAGHER | Approved | |
| 06/08/2020 | STUCCO MESH | WGALLAGHER | Approved | |
| 06/29/2020 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 06/29/2020 | FRAMING | DMUNIZ | Approved | Approved |
| 07/08/2020 | PLUMBING - ABOVE CEILING | DMUNIZ | Approved | ) Approved |
| 07/08/2020 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | Approved, Drain, Waste, & Vents under test ok to proceed. |
| 07/08/2020 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | ) Approved, Electrical Room Panels And Conduits Inspected. |
| 07/23/2020 | OUTDOOR LIGHTING FINAL | WGALLAGHER | Approved | CODE ECO |
| 07/23/2020 | ELECTRIC - UFER | WGALLAGHER | Approved | Approved |
| 07/23/2020 | ELECTRIC - UFER | TVALENCIA | Approved | Approved |
| 07/29/2020 | SHEET ROCK NAILING | TTREMBULAK | Approved | Approved |
| 07/31/2020 | PLUMBING - YARD WTR LINE/TEST | WGALLAGHER | Approved | Approved |
| 08/06/2020 | PLUMBING - MEDICAL GAS/TEST | DMUNIZ | Approved | Approved |
| 08/06/2020 | PLUMBING - MD GAS/PRECONST MTG | DMUNIZ | Approved | Approved |
| 09/04/2020 | REINFORCED MASONRY PRE-GROUT | WGALLAGHER | Approved | Approved |
| 09/04/2020 | FIREWALL/FIREBARRIER/FIRESTOP | WGALLAGHER | Approved | Approved |
| 09/04/2020 | ELECTRIC - ABOVE CEILING | WGALLAGHER | Approved | Approved |
| 09/04/2020 | MECHANICAL - ABOVE CEILING | WGALLAGHER | Approved | Approved |
| 10/20/2020 | GAS CLEARANCE | WGALLAGHER | Approved | Approved ok for clearance |
| 10/20/2020 | PLUMBING - GAS PRESS TEST FNL | WGALLAGHER | Approved | Approved ok for clearance |
| 10/20/2020 | ELECTRIC - OUTDOOR LIGHTING | WGALLAGHER | Approved | Approved |
| 10/20/2020 | ELECTRIC - CABLE DROP | WGALLAGHER | Approved | Approved |
| 10/20/2020 | BUILDING ABOVE CEILING | WGALLAGHER | Approved | Approved |
| 10/21/2020 | FIRE SPKLR - FINAL | jfordney | Approved | |
| 10/23/2020 | FIRE - ALARM FINAL | jfordney | Approved | |
| 10/27/2020 | FIRE - FINAL | CBASALDUA | Approved | |
| 10/29/2020 | TEP CLEARANCE - PM | TTREMBULAK | Approved | Not applicable. |
| 10/29/2020 | MECHANICAL - FINAL | TTREMBULAK | Approved | |
| 10/29/2020 | PLUMBING - FINAL | TTREMBULAK | Approved | |
| 10/29/2020 | NPPO - FINAL | RLEDONNE | Approved | |
| 10/29/2020 | SIGN - FINAL | RLEDONNE | Approved | |
| 10/29/2020 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 10/29/2020 | RIGHT OF WAY - FINAL | Bmong | Approved | |
| 11/10/2020 | ELECTRIC - FINAL | aquiroz | Approved | |
| 11/10/2020 | PLUMBING - MEDICAL GAS/FINAL | aquiroz | Approved | |
| 11/10/2020 | BUILDING PRE-SLAB | aquiroz | Approved | |
| 11/13/2020 | ENGINEERING - FINAL | DROBERTS | Approved | IS APPROVED AT THIS TIME. REMAINING LANDSCAPE ISSUES TO BE ADDRESSED WITH THE CLOSING OF THE DEVELOPMENT PACKAGE |
| 12/08/2020 | TEP CLEARANCE - AM | TTREMBULAK | Approved | Not applicable. |
| 12/08/2020 | BUILDING - FINAL | TTREMBULAK | Approved | Approved, pending special inspection results (sent in to Ken). |