Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 05/21/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
North, west, and south site foundation wall footers ok for concrete placement |
| 04/29/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
RVI |
| 04/15/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Partial approval light pole bases 7 each ok for concrete |
| 03/18/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Rebar in Building slab ok for concrete placement. |
| 03/13/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
curb detail for trench drain need approval stamp and ok to pour |
| 02/19/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
slab ok for concrete. |
| 02/07/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Exterior & Interior footings ok for concrete placement. |
| 02/05/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
Contractor rescheduled Via phone call. |