Permit: T19CM04550
Permit Details
Apply Date:
06/26/2019
Applicant:
TECHNICIANS FOR SUSTAINABILITY INC
Description:
PV CANOPY
Contractors:
- TECHNICIANS FOR SUSTAINABILITY INC
Permit Reviews
Permit Number - T19CM04550
Permit Status: Final
Permit Description: PV CANOPY
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/26/2019 | PLANS OK TO SUBMIT - COMM | 06/26/2019 | COMPLETED |
| 06/26/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/24/2019 | COMPLETED |
| 07/24/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/24/2019 | COMPLETED |
| 08/02/2019 | REVISION - - 1ST | 08/02/2019 | COMPLETED |
| 08/15/2019 | REVISION - - 2ND | 08/15/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM04550
Permit Status: Final
Permit Description: PV CANOPY
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/26/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM04550
Permit Description: PV CANOPY
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/20/2019 | ELECTRIC - UFER | BSTEVENS | Approved | (RVI) |
| 09/20/2019 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | (RVI) |
| 10/22/2019 | ENGINEERING - FINAL | BSTEVENS | Approved | (RVI) APPROVED BY BRIAN B |
| 10/22/2019 | BUILDING - FINAL | BSTEVENS | Approved | (RVI) |
| 10/22/2019 | ELECTRIC - FINAL | BSTEVENS | Approved | (RVI) |
| 10/22/2019 | OUTDOOR LIGHTING FINAL | BSTEVENS | Approved | |
| 10/22/2019 | ELECTRIC - OUTDOOR LIGHTING | BSTEVENS | Approved | |
| 10/22/2019 | ELECTRIC - INTERMEDIATE | BSTEVENS | Approved | |
| 10/22/2019 | ELECTRIC - UNDERGROUND | BSTEVENS | Approved | |
| 10/22/2019 | FRAMING | BSTEVENS | Approved | |
| 10/23/2019 | TEP CLEARANCE - AM | BSTEVENS | Approved | CODE DGL/DGC |