Permit: T19CM04215
Permit Details
Apply Date:
06/12/2019
Applicant:
Description:
UPGRADE EXISTING COMPRESSED NATURAL GAS FUELING STATION
Permit Reviews
Permit Number - T19CM04215
Permit Status: Issued
Permit Description: UPGRADE EXISTING COMPRESSED NATURAL GAS FUELING STATION
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/13/2019 | WALK THRU - COMM | 06/13/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM04215
Permit Status: Issued
Permit Description: UPGRADE EXISTING COMPRESSED NATURAL GAS FUELING STATION
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/12/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T19CM04215
Permite Description: UPGRADE EXISTING COMPRESSED NATURAL GAS FUELING STATION
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T19CM04215
Permit Description: UPGRADE EXISTING COMPRESSED NATURAL GAS FUELING STATION
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/27/2019 | COT - LCEL - Electrical Underground | Passed | {Activity date: 09/27/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - } | |
| 11/20/2019 | ENGR Engineering Final | Passed | {Activity date: 11/20/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } | |
| 12/05/2019 | COT - LCEL - Electrical Final | Passed | {Activity date: 12/05/2019; Status: Approved; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - } ; {Activity date: 11/20/2019; Status: Partial Approval; Inspector: JCLAXTON; Comment: Entered by DMERANZ1 - Seal all plugs. Recall with final} | |
| 10/19/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: CTREVIL; Comment: Entered by CTREVIL1 - } ; {Activity date: 09/19/2019; Status: Partial Approval; Inspector: TVALENCIA; Comment: Entered by VFLORES1 - Steel reinforcement provided for the mat at the CNG Compressor Pad located in the Equipment Compound} ; {Activity date: 09/11/2019; Status: Partial Approval; Inspector: TVALENCIA; Comment: Entered by DMERANZ1 - 1- Steel reinforcement provided and is okay for the Fuel Maker concrete pad only as noted on plans.} |