Inspection History Details
Inspection Status: Passed
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
Permit Number - T19CM04215
Inspection Description - COT - LCBU - Excavation/Rebar/Zoning
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/19/2022 | COT - LCBU - Excavation/Rebar/Zoning | CTREVIL | Approved | Entered by CTREVIL1 - |
09/19/2019 | COT - LCBU - Excavation/Rebar/Zoning | TVALENCIA | Partial Approval | Entered by VFLORES1 - Steel reinforcement provided for the mat at the CNG Compressor Pad located in the Equipment Compound |
09/11/2019 | COT - LCBU - Excavation/Rebar/Zoning | TVALENCIA | Partial Approval | Entered by DMERANZ1 - 1- Steel reinforcement provided and is okay for the Fuel Maker concrete pad only as noted on plans. |