Permit: T19CM04076
Permit Details
Status:
C of o
Type:
MULTI FAMILY NEW
Address:
9300 E VALENCIA RD #15
Address NEW:
9300 E VALENCIA RD #15
Apply Date:
06/06/2019
Applicant:
EGLIN, EVAN SAR
Description:
NEW APARTMENT BUILDING
Architects:
- EGLIN, EVAN SAR
Contractors:
- HSL CONSTRUCTION SERVICES LLC
Permit Reviews
Permit Number - T19CM04076
Permit Status: C of o
Permit Description: NEW APARTMENT BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/06/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 06/10/2019 | COMPLETED |
| 06/07/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/16/2019 | COMPLETED |
| 06/09/2020 | REVISION - - 3RD | 08/06/2020 | COMPLETED |
| 07/16/2019 | RESUBMITTAL | 09/16/2019 | COMPLETED |
| 09/16/2019 | REVISION - - 1ST | 09/19/2019 | COMPLETED |
| 10/02/2019 | REVISION - - 2ND | 10/08/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM04076
Permit Status: C of o
Permit Description: NEW APARTMENT BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/06/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM04076
Permit Description: NEW APARTMENT BUILDING
Total Completed Inspections - 35
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/17/2019 | PLUMBING - FINAL | RSHERRY | Approved | WATER DISINFECTION REPORT REQUIRED |
| 08/29/2019 | FIRE SPKLR - FINAL | MRoss | Approved | 1.5" copper riser 200psi tested |
| 09/05/2019 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | |
| 12/11/2019 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | |
| 12/11/2019 | ELECTRIC - UFER | DMUNIZ | Approved | #3/0 AWG Cu EGC connection to re-bar in footing ok to encase in concrete. |
| 12/26/2019 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | patio footings ok for concrete placement. |
| 12/31/2019 | BUILDING PRE-SLAB | DMUNIZ | Approved | RVI Inspection for center breezeway and stair footings. |
| 01/13/2020 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | |
| 04/28/2020 | ROOF NAILING | WGALLAGHER | Approved | |
| 05/26/2020 | BUILDING - PROGRESS | WGALLAGHER | Approved | Partial Approval For shower walls only, common wall, first floor for insulation in units 1,3,4,6 And unit 2 laundry drop ceiling area ok for insulation |
| 06/09/2020 | PLUMBING - YARD WTR LINE/TEST | DMUNIZ | Approved | |
| 06/29/2020 | EXT METAL CLIPS/EXT SHEATHING | DMUNIZ | Approved | Approved. |
| 06/29/2020 | FRAMING | DMUNIZ | Approved | Approved. |
| 06/29/2020 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | Approved, all units. |
| 06/29/2020 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | Approved, all units. |
| 06/29/2020 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | Approved, all units. |
| 07/08/2020 | TEP CLEARANCE - AM | ESTEVENS | Approved | CODE BUILDING 15 - UNITS: 15101, 15201,15301, 15102, 15202, 15302, 15103, 15203, 15303, 15104, 15204, 15304, 15105, 15205, 15305, 15106, 15206, 15306, 15107, 15207, 15307, 15108, 15208, AND 15308/ ECO |
| 07/08/2020 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | Approved, Clear TEP ECO BUILDING 15 - UNITS: 15101, 15201,15301, 15102, 15202, 15302, 15103, 15203, 15303, 15104, 15204, 15304, 15105, 15205, 15305, 15106, 15206, 15306, 15107, 15207, 15307, 15108, 15208, AND 15308 |
| 08/26/2020 | SHEET ROCK NAILING | WGALLAGHER | Approved | approved 3rd floor shear nailing on East and west end of building |
| 08/26/2020 | FIREWALL/FIREBARRIER/FIRESTOP | WGALLAGHER | Approved | Not ready |
| 10/26/2020 | ELECTRIC - PROGRESS | WGALLAGHER | Approved | Partial approval inspection for electrical TEP clearance to be recent For all units for building 15 |
| 10/26/2020 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE ECO: BUILDING 15 - UNITS: 15101, 15201,15301, 15102, 15202, 15302, 15103, 15203, 15303, 15104, 15204, 15304, 15105, 15205, 15305, 15106, 15206, 15306, 15107, 15207, 15307, 15108, 15208, AND 15308/ ECO |
| 12/14/2020 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
| 01/06/2021 | FIRE - ALARM FINAL | wmotto1 | Approved | 1. approved via face time |
| 01/06/2021 | FIRE - FINAL | wmotto1 | Approved | 1. approved via face time. |
| 01/08/2021 | U VALUE FOR WINDOW | RBOOHER | Approved | Approved. |
| 01/08/2021 | STUCCO MESH | RBOOHER | Approved | |
| 01/08/2021 | ELECTRIC - FINAL | RBOOHER | Approved | Approved. |
| 01/08/2021 | ELECTRIC - FINAL | RBOOHER | Approved | Please result all inspections as not ready. Called several times unable to locate a person of contact. |
| 01/12/2021 | BUILDING ABOVE CEILING | RCHANDLER | Approved | APPROVED |
| 01/12/2021 | BUILDING - FINAL | RCHANDLER | Approved | APPROVED |
| 01/12/2021 | OUTDOOR LIGHTING FINAL | RCHANDLER | Approved | APPROVED |
| 01/12/2021 | PLUMBING - ROOF DRAINS | RCHANDLER | Approved | APPROVED |
| 01/12/2021 | SITE - SEWER | RCHANDLER | Approved | APPROVED |
| 08/27/2021 | ENGINEERING - FINAL | DROBERTS | Approved | APPROVED PENDING ALL OTHER INSPECTIONS |