Permit: T19CM04065
Permit Details
Status:
C of o
Type:
MULTI FAMILY NEW
Address:
9300 E VALENCIA RD #07
Address NEW:
9300 E VALENCIA RD #07
Apply Date:
06/06/2019
Applicant:
EGLIN, EVAN SAR
Description:
NEW APARTMENT BUILDING
Architects:
- EGLIN, EVAN SAR
Permit Reviews
Permit Number - T19CM04065
Permit Status: C of o
Permit Description: NEW APARTMENT BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/06/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 06/10/2019 | COMPLETED |
| 06/09/2020 | REVISION - - 3RD | 08/06/2020 | COMPLETED |
| 06/13/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/16/2019 | COMPLETED |
| 07/16/2019 | RESUBMITTAL | 09/16/2019 | COMPLETED |
| 09/16/2019 | REVISION - - 1ST | 09/19/2019 | COMPLETED |
| 10/02/2019 | REVISION - - 2ND | 10/08/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM04065
Permit Status: C of o
Permit Description: NEW APARTMENT BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/06/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM04065
Permit Description: NEW APARTMENT BUILDING
Total Completed Inspections - 33
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/07/2019 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | |
| 04/01/2020 | ELECTRIC - UFER | WGALLAGHER | Approved | RVI |
| 04/01/2020 | BUILDING PRE-SLAB | WGALLAGHER | Approved | RVI |
| 04/01/2020 | EXCAVATION/LAYOUT REBAR & ZON | WGALLAGHER | Approved | RVI |
| 09/15/2020 | SITE - SEWER | TTREMBULAK | Approved | Approved |
| 09/15/2020 | PLUMBING - SEWER HCS CONNECT | TTREMBULAK | Approved | Approved |
| 12/14/2020 | FRAMING | TTREMBULAK | Approved | APPROVED |
| 12/14/2020 | EXT METAL CLIPS/EXT SHEATHING | TTREMBULAK | Approved | APPROVED |
| 12/14/2020 | ROOF NAILING | TTREMBULAK | Approved | APPROVED |
| 03/12/2021 | MECHANICAL - INTERMEDIATE | WGALLAGHER | Approved | |
| 03/12/2021 | PLUMBING - INTERMEDIATE | WGALLAGHER | Approved | |
| 03/12/2021 | U VALUE FOR WINDOW | WGALLAGHER | Approved | |
| 03/12/2021 | STUCCO MESH | WGALLAGHER | Approved | |
| 04/20/2021 | ELECTRIC - UNDERGROUND | RCHANDLER | Approved | |
| 04/20/2021 | FIREWALL/FIREBARRIER/FIRESTOP | RCHANDLER | Approved | |
| 04/23/2021 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | |
| 04/30/2021 | TEP CLEARANCE - PM | RCHANDLER | Approved | CODE/TMPP/BLDG #07 METER NUMBERS OW, 7101, 7102, 7103, 7104, 7105, 7106, 7108, 7201, 7202, 7203, 7204, 7205, 7206, 7207 |
| 04/30/2021 | ELECTRIC - PROGRESS | RCHANDLER | Approved | |
| 04/30/2021 | ELECTRIC - CONSTRUCTION POWER | RCHANDLER | Approved | |
| 05/27/2021 | TEP CLEARANCE - AM | RCHANDLER | Approved | CODE TMPP/BLDG #07 METER NUMBERS OW, 7101, 7102, 7103, 7104, 7105, 7106, 7108, 7201, 7202, 7203, 7204, 7205, 7206, 7207 |
| 07/28/2021 | BUILDING ABOVE CEILING | RCHANDLER | Approved | AP |
| 07/28/2021 | PLUMBING - ROOF DRAINS | RCHANDLER | Approved | AP |
| 07/28/2021 | PLUMBING - YARD WTR LINE/TEST | RCHANDLER | Approved | AP |
| 08/06/2021 | FIRE - ALARM FINAL | wmotto1 | Approved | |
| 08/06/2021 | FIRE SPKLR - FINAL | wmotto1 | Approved | |
| 08/06/2021 | FIRE - FINAL | wmotto1 | Approved | |
| 08/13/2021 | BUILDING - PROGRESS | WGALLAGHER | Approved | Approved |
| 08/13/2021 | ELECTRIC - FINAL | WGALLAGHER | Approved | Approved |
| 08/13/2021 | OUTDOOR LIGHTING FINAL | WGALLAGHER | Approved | Approved |
| 08/13/2021 | MECHANICAL - FINAL | WGALLAGHER | Approved | Approved |
| 08/16/2021 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
| 09/10/2021 | ENGINEERING - FINAL | MHERNANDEZ | Approved | APPROVED |
| 09/14/2021 | BUILDING - FINAL | WGALLAGHER | Approved | Approved |