Permit: T19CM03359
Permit Details
Apply Date:
05/10/2019
Applicant:
SOLON CORPORATION ***APA*** : FRANK ANZALUDA
Description:
PV SHADE CANOPIES
Contractors:
- SOLON CORPORATION ***APA***
Permit Reviews
Permit Number - T19CM03359
Permit Status: L of c
Permit Description: PV SHADE CANOPIES
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/10/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 06/12/2019 | ACTIVE |
| 05/10/2019 | PLANS OK TO SUBMIT - COMM | 05/10/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM03359
Permit Status: L of c
Permit Description: PV SHADE CANOPIES
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/10/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T19CM03359
Permit Description: PV SHADE CANOPIES
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/27/2019 | ELECTRIC - RECONNECT | DMUNIZ | Approved | PV Line side Tap in Existing 277/480V, 1200AMP SES From new fused 400AMP PV Utility Disconnect. 2 sets of Parallel Copper Conductors #250Kcmil , #1AWG Neutral, #1AWG Grnd. Verbal Clearance sent to TEP (RECN) @ 2:15AM. Upon arrival collected a check for $165 for after hours inspection. |
| 08/06/2019 | ELECTRIC - OUTDOOR LIGHTING | MHASSAN | Approved | |
| 08/06/2019 | ELECTRIC - INTERMEDIATE | MHASSAN | Approved | |
| 08/06/2019 | FRAMING | MHASSAN | Approved | |
| 08/06/2019 | ELECTRIC - UNDERGROUND | MHASSAN | Approved | |
| 08/06/2019 | ELECTRIC - UFER | MHASSAN | Approved | |
| 08/06/2019 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | |
| 08/09/2019 | TEP CLEARANCE - PM | MHASSAN | Approved | CODE DGC |
| 08/09/2019 | OUTDOOR LIGHTING FINAL | MHASSAN | Approved | |
| 08/09/2019 | ELECTRIC - FINAL | MHASSAN | Approved | OK to clear solar DGC |
| 08/09/2019 | BUILDING - FINAL | MHASSAN | Approved |