Permit: T19CM03325
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
9210 S HOUGHTON RD #102
Address NEW:
9210 S HOUGHTON RD #102
Apply Date:
05/09/2019
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI:RESTURANT
Contractors:
- BARKER CONTRACTING INC **APA**
Permit Reviews
Permit Number - T19CM03325
Permit Status: C of o
Permit Description: TI:RESTURANT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/09/2019 | PLANS OK TO SUBMIT - COMM | 05/10/2019 | COMPLETED |
| 05/10/2019 | 3RD PARTY REVIEW - COMMERCIAL TI | 06/24/2019 | COMPLETED |
| 06/24/2019 | POST 3RD PARTY REVIEW | 08/08/2019 | COMPLETED |
| 08/08/2019 | POST 3RD PARTY REVIEW | 08/09/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM03325
Permit Status: C of o
Permit Description: TI:RESTURANT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/09/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM03325
Permit Description: TI:RESTURANT
Total Completed Inspections - 30
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/14/2019 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | |
| 10/24/2019 | PLUMBING - PRE SLAB | DMUNIZ | Approved | |
| 10/24/2019 | BUILDING PRE-SLAB | DMUNIZ | Approved | |
| 03/19/2020 | SHEET ROCK NAILING | DQUINN | Approved | RVI |
| 07/10/2020 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 07/10/2020 | GAS CLEARANCE | DMUNIZ | Approved | CODE/#102 |
| 07/10/2020 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | Approved, Clear Southwest Gas. |
| 07/10/2020 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 07/10/2020 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | Approved, Electrical in walls. |
| 07/10/2020 | FRAMING | DMUNIZ | Approved | Approved |
| 07/10/2020 | NPPO - FINAL | RLEDONNE | Approved | Approved. |
| 07/10/2020 | SIGN - FINAL | RLEDONNE | Approved | Approved. |
| 07/10/2020 | LANDSCAPE - FINAL | RLEDONNE | Approved | Approved. |
| 07/17/2020 | RIGHT OF WAY - FINAL | BMONG | Approved | NO WORK IN RIGHT OF WAY |
| 07/28/2020 | MECHANICAL - HOODS | DMUNIZ | Approved | Approved, Smoke test complete ok to proceed. |
| 08/17/2020 | BUILDING ABOVE CEILING | DMUNIZ | Approved | Approved |
| 08/17/2020 | ELECTRIC - ABOVE CEILING | DMUNIZ | Approved | Approved |
| 08/17/2020 | PLUMBING - ABOVE CEILING | DMUNIZ | Approved | Approved |
| 08/17/2020 | PLUMBING - GAS PRESS TEST FNL | DMUNIZ | Approved | Approved |
| 08/17/2020 | MECHANICAL - ABOVE CEILING | DMUNIZ | Approved | Approved |
| 08/26/2020 | FIRE - KITCHEN EXH HOOD FINAL | wmotto | Approved | |
| 08/26/2020 | FIRE - ALARM FINAL | wmotto | Approved | |
| 08/26/2020 | FIRE SPKLR - FINAL | wmotto | Approved | |
| 09/04/2020 | ENGINEERING - FINAL | RLEDONNE | Approved | Approved. Accessible pathway from north side door of building to gate at West side of building. No chairs on tables on north side of patio only bench on north sideOf tables in order to achieve a clear 36 inch path. FaceTime inspection. |
| 09/04/2020 | MECHANICAL - FINAL | WGALLAGHER | Approved | Approved |
| 09/04/2020 | PLUMBING - FINAL | WGALLAGHER | Approved | Approved |
| 09/04/2020 | FIRE - FINAL | wmotto | Approved | |
| 09/09/2020 | MECHANICAL - HOOD SYSTEMS | TTREMBULAK | Approved | Approved |
| 09/09/2020 | ELECTRIC - FINAL | TTREMBULAK | Approved | Approved |
| 09/09/2020 | BUILDING - FINAL | TTREMBULAK | Approved | Approved |