Permit: T19CM02888
Permit Details
Apply Date:
04/23/2019
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
RETAIL
Architects:
- KURT SCHMITZ
Contractors:
- H R C: HEARTLAND RETAIL CONSTRUCTION
Permit Reviews
Permit Number - T19CM02888
Permit Status: C of o
Permit Description: RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/23/2019 | COMMERCIAL - TI | 05/07/2019 | COMPLETED |
05/07/2019 | 3RD PARTY REVIEW - COMMERCIAL TI | 05/29/2019 | COMPLETED |
05/29/2019 | POST 3RD PARTY REVIEW | 07/29/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM02888
Permit Status: C of o
Permit Description: RETAIL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/23/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM02888
Permit Description: RETAIL
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/12/2019 | PLUMBING - ROUGH, SOIL | MHASSAN | Approved | |
06/21/2019 | PLUMBING - INTERMEDIATE | MHASSAN | Approved | water test will still be needed on copper piping at above ceiling inspection |
06/21/2019 | ELECTRIC - INTERMEDIATE | MHASSAN | Approved | approval is for bathrooms and front office only |
06/21/2019 | FRAMING | MHASSAN | Approved | approval is for bathrooms and front office only |
06/27/2019 | BUILDING PRE-SLAB | MHASSAN | Approved | |
07/12/2019 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | approval is for above acoustical ceilings only. |
07/12/2019 | MECHANICAL - ABOVE CEILING | MHASSAN | Approved | approval is for above acoustical ceilings only. |
07/12/2019 | PLUMBING - ABOVE CEILING | MHASSAN | Approved | approval is for above acoustical ceilings only. |
07/12/2019 | ELECTRIC - ABOVE CEILING | MHASSAN | Approved | approval is for above acoustical ceilings only. |
07/12/2019 | SHEET ROCK NAILING | MHASSAN | Approved | approval is for above acoustical ceilings only. |
07/12/2019 | BUILDING ABOVE CEILING | MHASSAN | Approved | approval is for above acoustical ceilings only. |
07/19/2019 | NPPO - FINAL | BBENEDON | Approved | |
07/19/2019 | SIGN - FINAL | BBENEDON | Approved | |
07/19/2019 | LANDSCAPE - FINAL | BBENEDON | Approved | |
07/19/2019 | ENGINEERING - FINAL | BBENEDON | Approved | |
07/19/2019 | ELECTRIC - FINAL | MHASSAN | Approved | |
07/19/2019 | FIRE SPKLR - FINAL | Bravin | Approved | No issues |
07/29/2019 | PLUMBING - PRE SLAB | KROBLES | Approved | |
07/29/2019 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
07/30/2019 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
09/10/2019 | FIRE - ALARM FINAL | gsereno1 | Approved | Approved by CB 9/6/19 |
09/10/2019 | BUILDING - FINAL | TVALENCIA | Approved | PENDING FIRE FINALS |
09/10/2019 | RIGHT OF WAY - FINAL | Bravin | Approved | No issues or work in Right of way |
09/18/2019 | FIRE - FINAL | gsereno1 | Approved |