Permit: T19CM02762
Permit Details
Apply Date:
04/17/2019
Applicant:
L G I HOMES AZ CONSTRUCTION
Description:
SFR LGIH233318 T18-M0059
Contractors:
- L G I HOMES AZ CONSTRUCTION
Permit Reviews
Permit Number - T19CM02762
Permit Status: Final
Permit Description: SFR LGIH233318 T18-M0059
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/17/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 04/17/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM02762
Permit Status: Final
Permit Description: SFR LGIH233318 T18-M0059
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/17/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM02762
Permit Description: SFR LGIH233318 T18-M0059
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/14/2019 | PLUMBING - SEWER HCS CONNECT | AKLEINSORGE | Approved | Ok to backfill |
05/14/2019 | PLUMBING - YARD WTR LINE/TEST | AKLEINSORGE | Approved | Ok to backfill |
05/14/2019 | PLUMBING - ROUGH, SOIL | AKLEINSORGE | Approved | Ok to backfill |
05/20/2019 | BUILDING PRE-SLAB | AKLEINSORGE | Approved | Ok to pour concrete |
05/20/2019 | EXCAVATION/LAYOUT REBAR & ZON | AKLEINSORGE | Approved | Ok to pour concrete |
05/20/2019 | ELECTRIC - UNDERGROUND | AKLEINSORGE | Approved | |
05/20/2019 | ELECTRIC - UFER | AKLEINSORGE | Approved | |
06/10/2019 | ROOF NAILING | AKLEINSORGE | Approved | All corrections complete |
06/10/2019 | EXT METAL CLIPS/EXT SHEATHING | AKLEINSORGE | Approved | All corrections complete, except as follows: floor trusses not sitting flat on bearing wall top plates need shims and truss over stairs is not to code, contractor is going to move stairs back to allow for proper height clearance, both theses items can be inspected at framing inspection |
06/18/2019 | TEP CLEARANCE - PM | AKLEINSORGE | Approved | CODE ECO |
06/18/2019 | ELECTRIC - CONSTRUCTION POWER | AKLEINSORGE | Approved | CLEAR ECO |
06/26/2019 | MECHANICAL - INTERMEDIATE | AKLEINSORGE | Approved | |
06/26/2019 | GAS CLEARANCE | AKLEINSORGE | Approved | |
06/26/2019 | PLUMBING - GAS PRESSURE TEST | AKLEINSORGE | Approved | Clear gas please |
06/26/2019 | PLUMBING - INTERMEDIATE | AKLEINSORGE | Approved | 1. Secure toilet flanges |
06/26/2019 | RESIDENTIAL INTERMEDIATE | AKLEINSORGE | Approved | |
06/26/2019 | FRAMING | AKLEINSORGE | Approved | |
07/05/2019 | SHEET ROCK NAILING | AKLEINSORGE | Approved | |
08/09/2019 | MECHANICAL - FINAL | AKLEINSORGE | Approved | 1. Install rain proof cover on dryer vent 2. Paint all roof penetrations |
08/09/2019 | PLUMBING - FINAL | AKLEINSORGE | Approved | |
08/09/2019 | PLUMBING - PROGRESS | AKLEINSORGE | Approved | |
08/09/2019 | OUTDOOR LIGHTING FINAL | AKLEINSORGE | Approved | |
08/09/2019 | ELECTRIC - FINAL | AKLEINSORGE | Approved | 1. Address label at meter has been torn off, replace |
08/09/2019 | BUILDING - FINAL | AKLEINSORGE | Approved | 1. Install PT tag on water riser 2. Need house numbers installed |