Permit: T19CM02180
Permit Details
Status:
L of c
Type:
COMMERCIAL ALTERATION
Address:
350 S WILLIAMS BL
Address NEW:
350 S WILLIAMS BL
Apply Date:
03/28/2019
Applicant:
MATT WILLIAMS
Description:
TI:Office
Architects:
- A23 STUDIOS
Contractors:
- DIVISION II CONSTRUCTION COMPANY
Permit Reviews
Permit Number - T19CM02180
Permit Status: L of c
Permit Description: TI:Office
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/28/2019 | PLANS OK TO SUBMIT - COMM | 04/02/2019 | COMPLETED |
| 04/02/2019 | 3RD PARTY REVIEW - COMMERCIAL TI | 06/19/2019 | COMPLETED |
| 06/19/2019 | POST 3RD PARTY REVIEW | 07/03/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM02180
Permit Status: L of c
Permit Description: TI:Office
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/28/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T19CM02180
Permit Description: TI:Office
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/22/2019 | PLUMBING - ROUGH, SOIL | AKLEINSORGE | Approved | Ok to backfill over underground for Rooms 108 and 114 thru 118 |
| 09/10/2019 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | |
| 09/10/2019 | FRAMING | RCHANDLER | Approved | Also drywall. |
| 10/08/2019 | PLUMBING - ABOVE CEILING | JCLAXTON | Approved | Bathroom lids can be covered after confirmation from fire department that it is approved above ceiling in that area. |
| 10/08/2019 | PLUMBING - INTERMEDIATE | JCLAXTON | Approved | Bathrooms, break room. Ok to cover. |
| 10/08/2019 | SHEET ROCK NAILING | JCLAXTON | Approved | 1st and 2nd floor. Ok to mud. |
| 11/14/2019 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | |
| 11/14/2019 | PLUMBING - PRE SLAB | MRAMBER | Approved | |
| 11/26/2019 | MECHANICAL - ABOVE CEILING | RCHANDLER | Approved | |
| 12/10/2019 | BUILDING ABOVE CEILING | RCHANDLER | Approved | |
| 12/10/2019 | ELECTRIC - ABOVE CEILING | RCHANDLER | Approved | |
| 12/12/2019 | NPPO - FINAL | RLEDONNE | Approved | |
| 12/12/2019 | SIGN - FINAL | RLEDONNE | Approved | |
| 12/12/2019 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 12/12/2019 | ENGINEERING - FINAL | RLEDONNE | Approved | No work outside of building per approved plans. |
| 12/12/2019 | RIGHT OF WAY - FINAL | B Mong | Approved | No ROW issues . |
| 12/27/2019 | BUILDING - FINAL | MRAMBER | Approved | Complete all inspections including fire finals. Electrical OK at walls and offices, still need furniture/cubes and restrooms. Complete all plumbing In restrooms, need to complete for ADA. Unable to check mechanical on roof due to weather. |
| 12/27/2019 | ELECTRIC - FINAL | MRAMBER | Approved | Complete all inspections including fire finals. Electrical OK at walls and offices, still need furniture/cubes and restrooms. Complete all plumbing In restrooms, need to complete for ADA. Unable to check mechanical on roof due to weather. |
| 12/27/2019 | PLUMBING - FINAL | MRAMBER | Approved | Complete all inspections including fire finals. Electrical OK at walls and offices, still need furniture/cubes and restrooms. Complete all plumbing In restrooms, need to complete for ADA. Unable to check mechanical on roof due to weather. |
| 12/27/2019 | MECHANICAL - FINAL | MRAMBER | Approved | Complete all inspections including fire finals. Electrical OK at walls and offices, still need furniture/cubes and restrooms. Complete all plumbing In restrooms, need to complete for ADA. Unable to check mechanical on roof due to weather. |
| 01/03/2020 | FIRE - ALARM FINAL | gsereno1 | Approved | |
| 01/06/2020 | FIRE - FINAL | MRoss | Approved | |
| 01/06/2020 | FIRE SPKLR - FINAL | MRoss | Approved |