Permit: T19CM02154
Permit Details
Apply Date:
03/27/2019
Applicant:
JOSE L CEJA
Description:
NEW RESTAURANT
Contractors:
- CALDWELL CONSTRUCTION LLC
Permit Reviews
Permit Number - T19CM02154
Permit Status: L of c
Permit Description: NEW RESTAURANT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/27/2019 | PLANS OK TO SUBMIT - COMM | 06/17/2019 | COMPLETED |
| 06/17/2019 | COMMERCIAL - TI | 06/17/2019 | COMPLETED |
| 06/17/2019 | COMMERCIAL - TI | 08/23/2019 | COMPLETED |
| 08/23/2019 | RESUBMITTAL | 08/26/2019 | COMPLETED |
| 08/26/2019 | RESUBMITTAL | 09/24/2019 | COMPLETED |
| 11/05/2019 | REVISION - - 1ST | 11/05/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM02154
Permit Status: L of c
Permit Description: NEW RESTAURANT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/27/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T19CM02154
Permit Description: NEW RESTAURANT
Total Completed Inspections - 34
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/04/2019 | EXCAVATION/LAYOUT REBAR & ZON | RCHANDLER | Approved | |
| 11/04/2019 | ELECTRIC - UFER | RCHANDLER | Approved | |
| 11/08/2019 | STEM WALL/RETAINING WALL | RCHANDLER | Approved | |
| 11/19/2019 | PLUMBING - ROUGH, SOIL | RCHANDLER | Approved | Under slab ; HCS and site sewer remain to be inspected. |
| 12/13/2019 | PLUMBING - BACK WATER VALVE | RCHANDLER | Approved | |
| 12/13/2019 | PLUMBING - SEWER HCS CONNECT | RCHANDLER | Approved | |
| 12/16/2019 | ROOF NAILING | RCHANDLER | Approved | |
| 12/19/2019 | FRAMING | MRAMBER | Approved | Provide anchor bolts at bottom plate. |
| 12/19/2019 | ELECTRIC - CONSTRUCTION POWER | MRAMBER | Approved | |
| 12/19/2019 | ELECTRIC - TEMPORARY SERVICE | MRAMBER | Approved | |
| 12/19/2019 | ELECTRIC - UNDERGROUND | MRAMBER | Approved | No work at this time. |
| 12/26/2019 | PLUMBING - YARD WTR LINE/TEST | MRAMBER | Approved | |
| 12/26/2019 | EXT METAL CLIPS/EXT SHEATHING | MRAMBER | Approved | First layer exterior drywall OK |
| 01/10/2020 | GAS CLEARANCE | DMUNIZ | Approved | |
| 01/10/2020 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | Clear Southwest Gas. |
| 01/10/2020 | ELECTRIC - OUTDOOR LIGHTING | DMUNIZ | Approved | |
| 01/21/2020 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | |
| 01/21/2020 | ELECTRIC - ABOVE CEILING | MRAMBER | Approved | |
| 01/21/2020 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | |
| 01/22/2020 | PLUMBING - FINAL | WGALLAG1 | Approved | shell only |
| 01/23/2020 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | |
| 02/19/2020 | REINFORCED MASONRY PRE-GROUT | RCHANDLER | Approved | Retaining wall. |
| 02/24/2020 | U VALUE FOR WINDOW | RCHANDLER | Approved | |
| 04/02/2020 | TEP CLEARANCE - PM | RCHANDLER | Approved | CODE ECO METERS A,B, HP |
| 04/22/2020 | FIRE - FINAL | CBASALDUA | Approved | |
| 04/22/2020 | NPPO - FINAL | RLEDONNE | Approved | |
| 04/22/2020 | SIGN - FINAL | RLEDONNE | Approved | |
| 04/22/2020 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
| 04/22/2020 | MECHANICAL - FINAL | DMUNIZ | Approved | |
| 04/22/2020 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
| 04/22/2020 | ELECTRIC - FINAL | DMUNIZ | Approved | |
| 04/22/2020 | BUILDING - FINAL | DMUNIZ | Approved | |
| 04/23/2020 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 04/27/2020 | RIGHT OF WAY - FINAL | BMONG | Approved | ALL WORK WITHIN THE ROW IS IN SPEC |