Permit: T19CM01772
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
4940 E SPEEDWAY BL
Address NEW:
4940 E SPEEDWAY BL
Apply Date:
03/12/2019
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
RETAIL
Architects:
- GETZ, GRANT WILLIAM
Contractors:
- BLUE LION CONSTRUCTION L L C
Permit Reviews
Permit Number - T19CM01772
Permit Status: C of o
Permit Description: RETAIL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/12/2019 | COMMERCIAL - TI | 03/21/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM01772
Permit Status: C of o
Permit Description: RETAIL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/12/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM01772
Permit Description: RETAIL
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/04/2019 | PLUMBING - BACK WATER VALVE | GWEST | Approved | |
| 04/04/2019 | PLUMBING - ABOVE CEILING | GWEST | Approved | |
| 04/04/2019 | PLUMBING - INTERMEDIATE | GWEST | Approved | Toilet, lacy, mop sink, vent and drainage piping. Back flow valve installed and I place. |
| 04/16/2019 | GAS CLEARANCE | GWEST | Approved | SW Gas Clearance |
| 04/16/2019 | ELECTRIC - TEMPORARY SERVICE | GWEST | Approved | Needs PDSD. SW Gas Clearance, Reconnect Gas line replacement to roof TEP Clearance, INCR New 400Amp Service |
| 04/16/2019 | ELECTRIC - INTERMEDIATE | GWEST | Approved | Needs PDSD. SW Gas Clearance, Reconnect Gas line replacement to roof TEP Clearance, INCR New 400Amp Service |
| 04/16/2019 | PLUMBING - GAS PRESSURE TEST | GWEST | Approved | Needs PDSD. SW Gas Clearance, Reconnect Gas line replacement to roof TEP Clearance, INCR New 400Amp Service |
| 04/16/2019 | MECHANICAL - ABOVE CEILING | GWEST | Approved | Needs PDSD. SW Gas Clearance, Reconnect Gas line replacement to roof TEP Clearance, INCR New 400Amp Service |
| 05/30/2019 | TEP CLEARANCE - PM | MRAMBER | Approved | CODE INCR |
| 05/30/2019 | ELECTRIC - CONSTRUCTION POWER | MRAMBER | Approved | INCR ok to clear. |
| 06/07/2019 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | |
| 06/07/2019 | PLUMBING - FINAL | RCHANDLER | Approved | |
| 06/07/2019 | ELECTRIC - ABOVE CEILING | RCHANDLER | Approved | |
| 06/07/2019 | ELECTRIC - UNDERGROUND | RCHANDLER | Approved | |
| 06/07/2019 | ELECTRIC - UFER | RCHANDLER | Approved | |
| 06/07/2019 | BUILDING ABOVE CEILING | RCHANDLER | Approved | |
| 06/07/2019 | ENGINEERING - FINAL | RCAMACHO | Approved | No work outside of building perApproved plans. |
| 06/20/2019 | OUTDOOR LIGHTING FINAL | GWEST | Approved | |
| 06/20/2019 | ELECTRIC - FINAL | GWEST | Approved | |
| 06/20/2019 | ELECTRIC - OUTDOOR LIGHTING | GWEST | Approved | |
| 06/21/2019 | FIRE - FINAL | jvincent | Approved | added em light over rear door. |
| 06/24/2019 | MECHANICAL - FINAL | GWEST | Approved | Already done on 6-20-2019 The COT blurb. Upon all requirements and other dept approvals and signoffs this is all approved! |
| 06/24/2019 | BUILDING - FINAL | GWEST | Approved | Already done on 6-20-2019 The COT blurb. Upon all requirements and other dept approvals and signoffs this is all approved! |