Permit Details

Status:
Final
Type:
COMMERCIAL ADDITION
Address NEW:
8080 S HOUGHTON RD
Apply Date:
03/07/2019
Applicant:
KUBICEK, ROBERT
Description:
TI: REMODEL STORE (ADDING SQFT)
Contractors:
  • T K R L L C

Permit Reviews

Permit Number - T19CM01638
Permit Status: Final
Permit Description: TI: REMODEL STORE (ADDING SQFT)
Start Date Submittal Complete Date Status  
03/07/2019 PLANS OK TO SUBMIT - COMM 03/07/2019 COMPLETED Review Details
03/07/2019 COMMERCIAL - TI 05/02/2019 COMPLETED Review Details
05/02/2019 RESUBMITTAL 08/02/2019 COMPLETED Review Details

Completed Inspections

Permit Status: Final
Permit Number: T19CM01638
Permit Description: TI: REMODEL STORE (ADDING SQFT)
Total Completed Inspections - 26
Date Description Inspector Results Comments
08/13/2019 STEM WALL/RETAINING WALL DMUNIZ Approved Exterior Footings for stem walls, ok for concrete placement.
08/13/2019 EXCAVATION/LAYOUT REBAR & ZON DMUNIZ Approved Exterior Footings for stem walls, ok for concrete placement.
08/15/2019 PLUMBING - PRE SLAB DMUNIZ Approved
08/15/2019 ELECTRIC - UNDERGROUND DMUNIZ Approved
08/15/2019 REINFORCED MASONRY PRE-GROUT DMUNIZ Approved ok to grout.
08/16/2019 BUILDING PRE-SLAB DMUNIZ Approved ok for concrete placement.
08/27/2019 FRAMING DMUNIZ Approved
08/28/2019 EXT METAL CLIPS/EXT SHEATHING DMUNIZ Approved
09/06/2019 BUILDING ABOVE CEILING MRAMBER Approved
09/11/2019 MECHANICAL - INTERMEDIATE DMUNIZ Approved
09/11/2019 STUCCO MESH DMUNIZ Approved
12/12/2019 PLUMBING - ROUGH, SOIL DMUNIZ Approved
12/12/2019 ELECTRIC - ABOVE CEILING DMUNIZ Approved
12/12/2019 ELECTRIC - INTERMEDIATE DMUNIZ Approved
12/12/2019 ELECTRIC - SERVICE UPGRADE DMUNIZ Approved
12/12/2019 ELECTRIC - FINAL DMUNIZ Approved
12/20/2019 ENGINEERING - FINAL RLEDONNE Approved Development package DP19-0111 All work must be completed before I can sign off engineering final on this activate.
12/20/2019 BUILDING - FINAL DMUNIZ Approved Final pending approval from Fire, Health & Engineering.
12/20/2019 MECHANICAL - FINAL DMUNIZ Approved
12/20/2019 PLUMBING - FINAL DMUNIZ Approved
12/20/2019 PLUMBING - INTERMEDIATE DMUNIZ Approved
12/20/2019 BUILDING - PROGRESS DMUNIZ Approved
02/27/2020 FIRE SPKLR - FINAL jfordney Approved Approved by MRoss
08/13/2020 FIRE - FINAL wmotto Approved
08/13/2020 FIRE - ALARM FINAL wmotto Approved
09/10/2020 HEALTH DEPT - FINAL 724-7908 TTREMBULAK Approved