Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Apply Date:
02/26/2019
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
OFFICE
Contractors:
  • M A S DEVELOPMENT INC *APA*

Permit Reviews

Permit Number - T19CM01401
Permit Status: C of o
Permit Description: OFFICE
Start Date Submittal Complete Date Status  
02/26/2019 COMMERCIAL - TI 03/06/2019 COMPLETED Review Details
03/06/2019 3RD PARTY REVIEW - COMMERCIAL TI 03/19/2019 ACTIVE Review Details

Outstanding Activity Conditions

Permit Number - T19CM01401
Permit Status: C of o
Permit Description: OFFICE
Total Outstanding Activity Conditions - 1
Date Name
02/26/2019 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T19CM01401
Permit Description: OFFICE
Total Completed Inspections - 24
Date Description Inspector Results Comments
03/25/2019 PLUMBING - ROUGH, SOIL RCAMACHO Approved
04/05/2019 PLUMBING - ABOVE CEILING MHASSAN Approved
04/05/2019 PLUMBING - INTERMEDIATE MHASSAN Approved
04/05/2019 ELECTRIC - INTERMEDIATE MHASSAN Approved
04/05/2019 SHEET ROCK NAILING MHASSAN Approved
04/05/2019 FRAMING MHASSAN Approved
04/19/2019 MECHANICAL - ABOVE CEILING RCAMACHO Approved
04/19/2019 ELECTRIC - ABOVE CEILING RCAMACHO Approved
04/19/2019 BUILDING ABOVE CEILING RCAMACHO Approved
04/23/2019 NPPO - FINAL BBENEDON Approved
04/23/2019 SIGN - FINAL BBENEDON Approved
04/23/2019 LANDSCAPE - FINAL BBENEDON Approved
04/23/2019 ENGINEERING - FINAL BBENEDON Approved
04/23/2019 RIGHT OF WAY - FINAL DR Approved
04/30/2019 FIRE - ALARM FINAL gsereno1 Approved
04/30/2019 MECHANICAL - INTERMEDIATE RCAMACHO Approved
04/30/2019 PLUMBING - PRE SLAB RCAMACHO Approved
04/30/2019 ELECTRIC - FINAL GWEST Approved
05/02/2019 MECHANICAL - FINAL RSHERRY Approved REVIEW OF AIR BALANCE REPORT COMPLETED
05/02/2019 FIRE - FINAL gsereno1 Approved
05/02/2019 FIRE SPKLR - FINAL gsereno1 Approved
05/02/2019 MECHANICAL - FINAL RCAMACHO Approved pending air balance report to Bob Sherry
05/03/2019 BUILDING - FINAL AKLEINSORGE Approved
05/03/2019 PLUMBING - FINAL AKLEINSORGE Approved All corrections complete