Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T19CM01283
Permit Details
Apply Date:
02/21/2019
Applicant:
SOLON CORPORATION ***APA***
Description:
PV SHADE CANOPIES
Contractors:
- SOLON CORPORATION ***APA***
Permit Reviews
Permit Number - T19CM01283
Permit Status: Final
Permit Description: PV SHADE CANOPIES
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/21/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 03/20/2019 | ACTIVE |
02/21/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 02/21/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM01283
Permit Status: Final
Permit Description: PV SHADE CANOPIES
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/21/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM01283
Permit Description: PV SHADE CANOPIES
Total Completed Inspections - 11
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/09/2019 | EXCAVATION/LAYOUT REBAR & ZON | GWEST | Approved | 2x13 footings for 19 park and shade supports. 3 Ufers 20 wrapped |
05/09/2019 | ELECTRIC - UFER | GWEST | Approved | 2x13 footings for 19 park and shade supports. 3 Ufers 20 wrapped |
05/10/2019 | ELECTRIC - UNDERGROUND | RCHANDLER | Approved | |
05/22/2019 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
05/22/2019 | FRAMING | DQUINN | Approved | |
06/09/2019 | ELECTRIC - RECONNECT | DMUNIZ | Approved | Re-location and installation of 1200 AMP CT Meter Cabinet, New Sets of Parallel #500 MCM Conductors from Existing 120/208V Transformer to new CT Cabinet ok. New (2) sets of Parallel #600 MCM Conductors from New CT to Existing 800AMP SES OK, LINE Side Tap Approved .System Grounded and bonded Per NEC. Sent Verbal Clearance @ 10:45pm (RECN/DGL). Contractor to call in another inspection for Finals, Utility Disconnects not finished and to still be inspected prior to release of a Solar Meter (DGC). $165 Check received upon arrival of inspection (AFTERHOURS) |
06/11/2019 | BUILDING - FINAL | GWEST | Approved | ALL COT REQUIREMENTS COMPLETE |
06/11/2019 | OUTDOOR LIGHTING FINAL | GWEST | Approved | |
06/11/2019 | BUILDING - FINAL | GWEST | Approved | Approved upon meeting all COT requirements and other department approvals and sign offs. |
07/22/2019 | ELECTRIC - FINAL | DMUNIZ | Approved | Clear TEP (DGC) for 200 S Alvernon, ok to close this permit. Verbal Clearance sent in for 202 S Alvernon @ 7:59 PM (RECN). Check for $165 received upon arrival. |
08/22/2019 | TEP CLEARANCE - PM | AQUIROZ | Approved | TEPDG -13856 CODE DGC |