Permit: T19CM00615
Permit Details
Status:
C of o
Type:
MULTI FAMILY ALTERATION
Address:
1637 W EL RIO DR
Address NEW:
1637 W EL RIO DR
Apply Date:
01/28/2019
Applicant:
TODD, GARY DANIEL
Description:
NEW COMMUNITY BUILDING
Architects:
- TODD, GARY DANIEL
Contractors:
- WILSHIRE PACIFIC BUILDERS LLC
Permit Reviews
Permit Number - T19CM00615
Permit Status: C of o
Permit Description: NEW COMMUNITY BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/29/2019 | PLANS OK TO SUBMIT - COMM | 01/29/2019 | COMPLETED |
| 02/12/2019 | COMMERCIAL - NEW | 03/18/2019 | COMPLETED |
| 03/27/2019 | RESUBMITTAL | 05/01/2019 | COMPLETED |
| 05/01/2019 | RESUBMITTAL | 05/02/2019 | COMPLETED |
| 05/02/2019 | OTHER | 05/31/2019 | COMPLETED |
| 09/26/2019 | REVISION - - 1ST | 09/26/2019 | COMPLETED |
| 09/26/2019 | REVISION - - 1ST | 11/18/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM00615
Permit Status: C of o
Permit Description: NEW COMMUNITY BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/28/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM00615
Permit Description: NEW COMMUNITY BUILDING
Total Completed Inspections - 31
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/06/2019 | PLUMBING - ROUGH, SOIL | TVALENCIA | Approved | |
| 08/06/2019 | PLUMBING - SEWER HCS CONNECT | TVALENCIA | Approved | |
| 09/16/2019 | FRAMING | DQUINN | Approved | |
| 09/16/2019 | ROOF NAILING | DQUINN | Approved | |
| 09/30/2019 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 09/30/2019 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 09/30/2019 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
| 10/04/2019 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | |
| 10/04/2019 | ELECTRIC - UNDERGROUND | DQUINN | Approved | |
| 10/08/2019 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | |
| 10/21/2019 | BUILDING PRE-SLAB | BSTEVENS | Approved | (RVI) FOOTINGS FOR A/C AND POOL EQUIPMENT SCREEN WALLS |
| 10/21/2019 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | (RVI) FOOTINGS FOR A/C AND POOL EQUIPMENT SCREEN WALLS |
| 11/14/2019 | TEP CLEARANCE - PM | DQUINN | Approved | CODE ECO |
| 11/14/2019 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | Clear eco |
| 11/19/2019 | REINFORCED MASONRY PRE-GROUT | BSTEVENS | Approved | SCREEN WALLS FOR EQUIPMENT OK TO GROUT TO TOP |
| 12/19/2019 | SEPTIC - SYSTEM | DQUINN | Approved | |
| 12/19/2019 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | |
| 12/19/2019 | ELECTRIC - PROGRESS | DQUINN | Approved | |
| 12/19/2019 | ELECTRIC - TEMPORARY SERVICE | DQUINN | Approved | |
| 12/19/2019 | ELECTRIC - UFER | DQUINN | Approved | |
| 12/19/2019 | BUILDING - PROGRESS | DQUINN | Approved | |
| 12/19/2019 | U VALUE FOR WINDOW | DQUINN | Approved | |
| 12/19/2019 | STUCCO MESH | DQUINN | Approved | |
| 12/19/2019 | BUILDING ABOVE CEILING | DQUINN | Approved | |
| 12/19/2019 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
| 12/20/2019 | ELECTRIC - FINAL | TVALENCIA | Approved | |
| 12/27/2019 | PLUMBING - FINAL | DQUINN | Approved | All above partialled inspections to be approved with completion of certs and permit closed. |
| 12/27/2019 | MECHANICAL - FINAL | DQUINN | Approved | All above partialled inspections to be approved with completion of certs and permit closed. |
| 12/27/2019 | CERTIFICATE OF OCCUPANCY | DQUINN | Approved | All above partialled inspections to be approved with completion of certs and permit closed. |
| 12/27/2019 | BUILDING - FINAL | DQUINN | Approved | All above partialled inspections to be approved with completion of certs and permit closed. |
| 12/27/2019 | OUTDOOR LIGHTING FINAL | DQUINN | Approved |