Permit Details

Status:
Final
Type:
Barricade and Excavation
Apply Date:
11/13/2018
Applicant:
N/A
Description:
REMOVAL OF SIDEWALK ON AVENIDA DEL CONVENTO, SOUTH SIDE OF PASEO DE LOS ZANJEROS, AND NORTH SIDEWALK ON CALLE DE LOS HIGOS. ALSO BENCHING IN ROW FOR UNDERGROUND FACILITIES. SEE T18RW04879 FOR BARRICADING 03/14/2019-PLAN CHANGE DUE TO WEATHER, NEED TO CLOSE STREET FOR SLAB ON GRADE CONCRETE POUR. TO CLOSE 6 HOURS ON SATURDAY 03/16/2019
Contractors:
  • DAY'S EXCAVATING INC
  • LLOYD CONSTRUCTION COMPANY INC *** APA ***

Completed Inspections

Permit Status: Final
Permit Number: T18RW05071
Permit Description: REMOVAL OF SIDEWALK ON AVENIDA DEL CONVENTO, SOUTH SIDE OF PASEO DE LOS ZANJEROS, AND NORTH SIDEWALK ON CALLE DE LOS HIGOS. ALSO BENCHING IN ROW FOR UNDERGROUND FACILITIES. SEE T18RW04879 FOR BARRICADING 03/14/2019-PLAN CHANGE DUE TO WEATHER, NEED TO CLOSE STREET FOR SLAB ON GRADE CONCRETE POUR. TO CLOSE 6 HOURS ON SATURDAY 03/16/2019
Total Completed Inspections - 1
Date Description Inspector Results Comments
12/20/2018 TDOT-EXCAV GENERAL INSPECTION cfarren1 Approved contractor working and traffic control up per plan - CN