Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 08/15/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Permit calls for removal of sidewalk which was complete. Fencing still in place, and concrete pour on permit has been completed. Per permit work is complete |
| 12/20/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
contractor working and traffic control up per plan - CN |
| 12/18/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
meet with dennis about traffic control - CN |
| 11/15/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
had pre-con - talked about work that will be done - CN |