Permit Number - T18CM10030
Permit Status: Final
Permit Description: BED ROOM ADDITION
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/28/2018 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 12/28/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM10030
Permit Status: Final
Permit Description: BED ROOM ADDITION
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/28/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM10030
Permit Description: BED ROOM ADDITION
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/18/2019 | EXCAVATION/LAYOUT REBAR & ZON | RCHANDLER | Approved | |
| 03/22/2019 | STEM WALL/RETAINING WALL | GWEST | Approved | all good |
| 03/22/2019 | STEM WALL/RETAINING WALL | GWEST | Approved | No answer at either front doors. Loud music playing. Went to back, looked for plans, none found. |
| 04/09/2019 | PLUMBING - ROUGH, SOIL | MRAMBER | Approved | |
| 04/19/2019 | BUILDING PRE-SLAB | DQUINN | Approved | |
| 06/26/2019 | ROOF NAILING | MRAMBER | Approved | |
| 09/23/2019 | EXT METAL CLIPS/EXT SHEATHING | RCHANDLER | Approved | |
| 11/21/2019 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | |
| 11/21/2019 | PLUMBING - INTERMEDIATE | RCHANDLER | Approved | |
| 11/21/2019 | RESIDENTIAL INTERMEDIATE | RCHANDLER | Approved | |
| 11/21/2019 | FRAMING | RCHANDLER | Approved | |
| 12/04/2019 | PLUMBING - GAS PRESS TEST FNL | RCHANDLER | Approved | |
| 12/04/2019 | PLUMBING - GAS PRESSURE TEST | RCHANDLER | Approved | OK to set meter. |
| 12/04/2019 | PLUMBING - YARD WTR LINE/TEST | RCHANDLER | Approved | |
| 02/21/2020 | MECHANICAL - FINAL | MRAMBER | Approved | |
| 02/21/2020 | PLUMBING - FINAL | MRAMBER | Approved | |
| 02/21/2020 | ELECTRIC - FINAL | MRAMBER | Approved | |
| 02/21/2020 | OUTDOOR LIGHTING FINAL | MRAMBER | Approved | |
| 02/21/2020 | BUILDING - FINAL | MRAMBER | Approved |