Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Expired
Type:
Commercial Building
Address NEW:
265 W NEBRASKA ST
Apply Date:
12/27/2018
Applicant:
Description:
E-INSTALL COMM. PV SYSTEM AND RELATED EQUIPMENT 265 W NEBRASKA ST. APOLLO MIDDLE SCHOOL

Permit Reviews

Permit Number - T18CM10028
Permit Status: Expired
Permit Description: E-INSTALL COMM. PV SYSTEM AND RELATED EQUIPMENT 265 W NEBRASKA ST. APOLLO MIDDLE SCHOOL
Start Date Submittal Complete Date Status  
02/26/2019 RESUBMITTAL 03/22/2019 COMPLETED Review Details
04/25/2019 REVISION - - 1ST 04/25/2019 COMPLETED Review Details
12/27/2018 WALK THRU - COMM 01/30/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM10028
Permit Status: Expired
Permit Description: E-INSTALL COMM. PV SYSTEM AND RELATED EQUIPMENT 265 W NEBRASKA ST. APOLLO MIDDLE SCHOOL
Total Outstanding Activity Conditions - 1
Date Name
12/27/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Conditions

Permit Number - T18CM10028
Permit Status: Expired
Permit Description: E-INSTALL COMM. PV SYSTEM AND RELATED EQUIPMENT 265 W NEBRASKA ST. APOLLO MIDDLE SCHOOL
Date Description Comments
12/27/2018 SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY.
12/27/2018 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
12/27/2018 SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED.

Completed Inspections

Permit Status: Expired
Permit Number: T18CM10028
Permit Description: E-INSTALL COMM. PV SYSTEM AND RELATED EQUIPMENT 265 W NEBRASKA ST. APOLLO MIDDLE SCHOOL
Total Completed Inspections - 10
Date Description Inspector Results Comments
04/23/2019 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 04/23/2019; Status: Approved; Inspector: MHASSAN; Comment: Entered by CBELL1 - }
07/24/2019 COT - LCEL - Electrical Underground Passed {Activity date: 07/24/2019; Status: Approved; Inspector: MHASSAN; Comment: Entered by DMERANZ1 - } ; {Activity date: 07/18/2019; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VFLORES1 - Electrical underground Conduits from Canopy 1-5 OK to encase and backfill.}
08/20/2019 COT - LCBU - Framing Passed {Activity date: 08/20/2019; Status: Approved; Inspector: MHASSAN; Comment: Entered by DMERANZ1 - } ; {Activity date: 05/03/2019; Status: Partial Approval; Inspector: MHASSAN; Comment: Entered by CBELL1 - except southern array}
08/20/2019 COT - LCBU - Roof Nailing Passed {Activity date: 08/20/2019; Status: Approved; Inspector: MHASSAN; Comment: Entered by DMERANZ1 - } ; {Activity date: 05/03/2019; Status: Partial Approval; Inspector: MHASSAN; Comment: Entered by CBELL1 - except southern array}
08/24/2019 COT - LCBU - Building Final Passed {Activity date: 08/24/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - }
08/24/2019 COT - LCEL - Electrical Intermediate Passed {Activity date: 08/24/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Interconnection from New PV Utility Disconnect to Existing 1600AMP SES.
Third party on site to re certify Gear.
Verbal Clearance sent to TEP @ 10:10AM (RECN).
Please submit Clearance for DGC.}
08/24/2019 COT - LCEL - Outdoor Lighting Passed {Activity date: 08/24/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Interconnection from New PV Utility Disconnect to Existing 1600AMP SES.
Third party on site to re certify Gear.
Verbal Clearance sent to TEP @ 10:10AM (RECN).
Please submit Clearance for DGC.}
08/24/2019 COT - LCEL - Electrical Final Passed {Activity date: 08/24/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Interconnection from New PV Utility Disconnect to Existing 1600AMP SES.
Third party on site to re certify Gear.
Verbal Clearance sent to TEP @ 10:10AM (RECN).
Please submit Clearance for DGC.} ; {Activity date: 08/20/2019; Status: Partial Approval; Inspector: MHASSAN; Comment: Entered by DMERANZ1 - pending all labels and labeling being completed.}
08/24/2019 COT - LCEL - Grounding/Bonding Passed {Activity date: 08/24/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Interconnection from New PV Utility Disconnect to Existing 1600AMP SES.
Third party on site to re certify Gear.
Verbal Clearance sent to TEP @ 10:10AM (RECN).
Please submit Clearance for DGC.} ; {Activity date: 07/18/2019; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VFLORES1 - #4CU GEC from Canopy 1-5 crimped, bonded and Approved} ; {Activity date: 04/23/2019; Status: Approved; Inspector: MHASSAN; Comment: Entered by CBELL1 - }
08/26/2019 BULD - Electrical Clearance Passed {Activity date: 08/26/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - CODE DGC}

Documents

File Name Document Type  
2_APOLLO MIDDLE SCHOOL SOLAR PLAN SET.PDF CONSTRPLANS VIEW
001_S1.TIF CONSTRPLANS VIEW
002_S2.TIF CONSTRPLANS VIEW
003_S3.TIF CONSTRPLANS VIEW
004_S4.TIF CONSTRPLANS VIEW
005_S5.TIF CONSTRPLANS VIEW
None DOCUMENTS VIEW
1_CONTRACTOR CONFIRMATION LETTER.PDF DOCUMENTS VIEW
1_PERMIT_APPLICATION.PDF DOCUMENTS VIEW
1_STRUCTURAL SPECIAL INSPECTION CERT.PDF DOCUMENTS VIEW
2_SUSD APOLLO STRUCTUAL CALCS SEALED_REVISED 1.26.19.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
SOILS REPORT.PDF DOCUMENTS VIEW
None DOCUMENTS VIEW