Permit: T18CM10010
Permit Details
Apply Date:
12/27/2018
Applicant:
N/A
Description:
REPLACE CANOPY
Contractors:
- LYTLE ELECTRIC L L C
Permit Reviews
Permit Number - T18CM10010
Permit Status: L of c
Permit Description: REPLACE CANOPY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/09/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 03/08/2019 | COMPLETED |
07/12/2019 | REVISION - - 1ST | 08/13/2019 | COMPLETED |
08/13/2019 | REVISION - - 2ND | 08/19/2019 | COMPLETED |
12/27/2018 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 12/28/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM10010
Permit Status: L of c
Permit Description: REPLACE CANOPY
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/27/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T18CM10010
Permit Description: REPLACE CANOPY
Total Completed Inspections - 12
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/06/2019 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | All canopy casons ok to pour |
10/02/2019 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | |
10/02/2019 | FRAMING | DQUINN | Approved | |
10/02/2019 | ROOF NAILING | DQUINN | Approved | |
10/11/2019 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | Underground cox cable extension, and all underground under new canopy to pay station islands ok to backfill. |
10/11/2019 | ELECTRIC - UNDERGROUND | DQUINN | Approved | Underground cox cable extension, and all underground under new canopy to pay station islands ok to backfill. |
10/21/2019 | BUILDING - PROGRESS | DQUINN | Approved | |
10/21/2019 | FIRE - FINAL | jvincent | Approved | |
10/25/2019 | ELECTRIC - FINAL | DQUINN | Approved | |
11/27/2019 | BUILDING - FINAL | ESTEVENS | Approved | |
11/27/2019 | BUILDING - FINAL | ESTEVENS | Approved | APPROVED BY INSPECTORS, CLOSURE OF THIS PERMIT IS PENDING DUE TO THE OUTSTANDING SPECIAL INSPECTION CERTIFICATES REQUIRED. |
11/27/2019 | ENGINEERING - FINAL | BBENEDON | Approved |