Permit: T18CM09927
Permit Details
Apply Date:
12/21/2018
Applicant:
N/A
Description:
Facility Connection to TW Cenertal System
Contractors:
- HERMAN CONTRACTING INC
Permit Reviews
Permit Number - T18CM09927
Permit Status: L of c
Permit Description: Facility Connection to TW Cenertal System
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/30/2019 | RESUBMITTAL | 03/13/2019 | COMPLETED |
12/21/2018 | PLANS OK TO SUBMIT - COMM | 12/21/2018 | COMPLETED |
12/24/2018 | COMMERCIAL - TI | 01/29/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM09927
Permit Status: L of c
Permit Description: Facility Connection to TW Cenertal System
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/21/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T18CM09927
Permit Description: Facility Connection to TW Cenertal System
Total Completed Inspections - 18
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/24/2019 | ELECTRIC - UFER | AKLEINSORGE | Approved | Ok to pour control room footings/floor |
04/24/2019 | EXCAVATION/LAYOUT REBAR & ZON | AKLEINSORGE | Approved | |
05/10/2019 | ELECTRIC - UNDERGROUND | AKLEINSORGE | Approved | Power trench east of control room and north of control room. |
05/15/2019 | REINFORCED MASONRY PRE-GROUT | DMUNIZ | Approved | Ok to grout second lift. |
06/05/2019 | FRAMING | AKLEINSORGE | Approved | Control building concrete roof, ok to place concrete |
12/11/2019 | FIRE - FINAL | jvincent | Approved | |
12/11/2019 | BUILDING - FINAL | TVALENCIA | Approved | APPROVED BY INSPECTOR PENDING FIRE FINAL & SPECIAL INSPECTION CERTIFICATES & WATER DISINFECTION REPORT |
12/11/2019 | NPPO - FINAL | RLEDONNE | Approved | |
12/11/2019 | ENGINEERING - FINAL | RLEDONNE | Approved | |
12/11/2019 | ELECTRIC - CONSTRUCTION POWER | TVALENCIA | Approved | |
12/11/2019 | ELECTRIC - OUTDOOR LIGHTING | TVALENCIA | Approved | |
12/11/2019 | OUTDOOR LIGHTING FINAL | TVALENCIA | Approved | |
12/11/2019 | ELECTRIC - INTERMEDIATE | TVALENCIA | Approved | |
12/11/2019 | ELECTRIC - FINAL | TVALENCIA | Approved | |
12/11/2019 | MECHANICAL - FINAL | TVALENCIA | Approved | |
12/11/2019 | MECHANICAL - INTERMEDIATE | TVALENCIA | Approved | |
12/11/2019 | PLUMBING - INTERMEDIATE | TVALENCIA | Approved | |
12/11/2019 | PLUMBING - FINAL | TVALENCIA | Approved | APPROVED BY INSPECTOR PENDING WATER REPORT APPROVAL |