Permit: T18CM09193
Permit Details
Apply Date:
11/20/2018
Applicant:
GONZALEZ, RICKY LINN
Description:
CARE HOME
Architects:
- GONZALEZ, RICKY LINN
Contractors:
- RALCON LLC
Permit Reviews
Permit Number - T18CM09193
Permit Status: C of o
Permit Description: CARE HOME
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/12/2019 | COMMERCIAL - TI | 03/18/2019 | COMPLETED |
| 03/18/2019 | RESUBMITTAL | 03/20/2019 | ACTIVE |
| 11/20/2018 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 12/17/2018 | COMPLETED |
| 12/17/2018 | COMMERCIAL - TI | 02/11/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM09193
Permit Status: C of o
Permit Description: CARE HOME
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/20/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM09193
Permit Description: CARE HOME
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/09/2019 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | Ok to cover progress areas. |
| 05/15/2019 | ELECTRIC - ABOVE CEILING | RCHANDLER | Approved | |
| 05/15/2019 | BUILDING ABOVE CEILING | RCHANDLER | Approved | |
| 05/15/2019 | ELECTRIC - ABOVE CEILING | RCHANDLER | Approved | |
| 05/17/2019 | PLUMBING - INTERMEDIATE | RCHANDLER | Approved | |
| 05/17/2019 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | |
| 05/29/2019 | MECHANICAL - INTERMEDIATE | AKLEINSORGE | Approved | |
| 05/29/2019 | FRAMING | AKLEINSORGE | Approved | |
| 08/07/2019 | FIRE SPKLR - FINAL | MRoss | Approved | |
| 08/14/2019 | ELECTRIC - FINAL | DQUINN | Approved | |
| 08/14/2019 | CERTIFICATE OF OCCUPANCY | DQUINN | Approved | Partial results can be finalled when Mr. Sherry’s reviews are approved and fire is approved. |
| 08/14/2019 | BUILDING - PROGRESS | DQUINN | Approved | |
| 08/14/2019 | CERTIFICATE OF OCCUPANCY | DQUINN | Approved | |
| 09/11/2019 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
| 09/27/2019 | FIRE - ALARM FINAL | gsereno1 | Approved | |
| 10/08/2019 | FIRE - FINAL | CBASALDUA | Approved | |
| 10/11/2019 | MECHANICAL - FINAL | JBURGE | Approved | One init split system. |
| 10/11/2019 | BUILDING - FINAL | JBURGE | Approved | Ok to make application for Certificate of Occupancy. |