Permit: T18CM09121
Permit Details
Apply Date:
11/16/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW EXECUTIVE TERMINAL AND HANGAR
Architects:
- FRANKS, MICHAEL WILLIAM
Permit Reviews
Permit Number - T18CM09121
Permit Status: C of o
Permit Description: NEW EXECUTIVE TERMINAL AND HANGAR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/19/2019 | POST 3RD PARTY REVIEW | 02/22/2019 | COMPLETED |
| 02/22/2019 | POST 3RD PARTY REVIEW | 04/18/2019 | COMPLETED |
| 04/18/2019 | POST 3RD PARTY REVIEW | 05/01/2019 | COMPLETED |
| 11/16/2018 | PLANS OK TO SUBMIT - COMM | 12/10/2018 | COMPLETED |
| 12/11/2018 | 3RD PARTY REVIEW - COMMERCIAL TI | 02/19/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM09121
Permit Status: C of o
Permit Description: NEW EXECUTIVE TERMINAL AND HANGAR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/16/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM09121
Permit Description: NEW EXECUTIVE TERMINAL AND HANGAR
Total Completed Inspections - 41
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/04/2019 | ELECTRIC - UNDERGROUND | TVALENCIA | Approved | 1- Underground electric conduits are okay to cover between grid lines H to 2 and from the Transformer to the CT Can and to Electric Room 304. |
| 10/25/2019 | PLUMBING - ROUGH, SOIL | TVALENCIA | Approved | |
| 11/05/2019 | ELECTRIC - UFER | TVALENCIA | Approved | 1- Ufer ground conductor provided. |
| 12/06/2019 | PLUMBING - PRE SLAB | TVALENCIA | Approved | 1-Building service water supply okay to cover. |
| 12/16/2019 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | Terminal area stem wall |
| 12/20/2019 | BUILDING PRE-SLAB | WGALLAGHER | Approved | |
| 03/17/2020 | FRAMING | TVALENCIA | Approved | |
| 03/17/2020 | ROOF NAILING | TVALENCIA | Approved | |
| 04/08/2020 | ELECTRIC - CABLE DROP | TVALENCIA | Approved | |
| 04/08/2020 | FIREWALL/FIREBARRIER/FIRESTOP | TVALENCIA | Approved | |
| 04/08/2020 | EXT METAL CLIPS/EXT SHEATHING | TVALENCIA | Approved | |
| 04/13/2020 | PLUMBING - ABOVE CEILING | TVALENCIA | Approved | |
| 04/13/2020 | PLUMBING - INTERMEDIATE | TVALENCIA | Approved | |
| 04/20/2020 | PLUMBING - SEWER HCS CONNECT | WGALLAGHER | Approved | Approved ok to cover |
| 04/21/2020 | MECHANICAL - ABOVE CEILING | TTREMBULAK | Approved | RVI |
| 04/21/2020 | MECHANICAL - INTERMEDIATE | TTREMBULAK | Approved | RVI |
| 04/22/2020 | ELECTRIC - ABOVE CEILING | TVALENCIA | Approved | |
| 04/22/2020 | ELECTRIC - INTERMEDIATE | TVALENCIA | Approved | |
| 05/06/2020 | SHEET ROCK NAILING | DMUNIZ | Approved | |
| 05/12/2020 | TEP CLEARANCE - PM | TVALENCIA | Approved | CODE ECO |
| 07/17/2020 | NPPO - FINAL | BBENEDON | Approved | Approved |
| 07/17/2020 | PLUMBING - MD GAS/PRECONST MTG | DMUNIZ | Approved | Not Applicable. |
| 07/17/2020 | PLUMBING - ROOF DRAINS | DMUNIZ | Approved | Approved. |
| 07/17/2020 | STUCCO MESH | DMUNIZ | Approved | Not Applicable. |
| 07/17/2020 | BUILDING ABOVE CEILING | DMUNIZ | Approved | Approved |
| 07/17/2020 | STEM WALL/RETAINING WALL | DMUNIZ | Approved | Approved |
| 07/17/2020 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | Approved |
| 07/17/2020 | ELECTRIC - FINAL | DMUNIZ | Approved | Approved |
| 07/17/2020 | ELECTRIC - OUTDOOR LIGHTING | DMUNIZ | Approved | Approved |
| 07/17/2020 | U VALUE FOR WINDOW | DMUNIZ | Approved | Approved |
| 07/17/2020 | RIGHT OF WAY - FINAL | Bravin | Approved | No issues |
| 07/27/2020 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
| 07/27/2020 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
| 07/29/2020 | SIGN - FINAL | BBENEDON | Approved | Approved |
| 07/29/2020 | LANDSCAPE - FINAL | BBENEDON | Approved | Approved |
| 07/30/2020 | ENGINEERING - FINAL | BBENEDON | Approved | Approved |
| 08/03/2020 | FIRE - FINAL | CBASALDUA | Approved | |
| 08/03/2020 | FIRE - FINAL | CBASALDUA | Approved | 1. Awaiting permit for monitoring of Fire Alarm system. 2. Alarm and monitoring were installed in by two different contractors. |
| 08/03/2020 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 08/03/2020 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 08/05/2020 | BUILDING - FINAL | BSTEVENS | Approved |