Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 06/10/2020 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
|
| 12/16/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Terminal area stem wall |
| 11/22/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Exterior footings per schedule & ok for concrete placement. |
| 11/05/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
1- Steel reinforcement in the Hanger is okay. |
| 10/15/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
1- Steel reinforcement okay for the Hanger footings and two South Terminator al footings only. |