Permit: T18CM09086
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
6569 E CARONDELET DR
Address NEW:
6569 E CARONDELET DR
Apply Date:
11/15/2018
Applicant:
BRIGHT, RICK LANE
Description:
TI: CONVENT TO ASSISTED LIVING- FULL OCCUPANCY
Contractors:
- STERLING BUILDING AND DESIGN LLC
Outstanding Activity Conditions
Permit Number - T18CM09086
Permit Status: C of o
Permit Description: TI: CONVENT TO ASSISTED LIVING- FULL OCCUPANCY
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/15/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM09086
Permit Description: TI: CONVENT TO ASSISTED LIVING- FULL OCCUPANCY
Total Completed Inspections - 41
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/28/2019 | PLUMBING - ROUGH, SOIL | MRAMBER | Approved | |
| 06/07/2019 | SITE - SEWER | RCHANDLER | Approved | |
| 06/07/2019 | ELECTRIC - UFER | RCHANDLER | Approved | |
| 08/19/2019 | BUILDING ABOVE CEILING | MRAMBER | Approved | |
| 08/19/2019 | BUILDING PRE-SLAB | MRAMBER | Approved | |
| 08/21/2019 | PLUMBING - PRE SLAB | RCHANDLER | Approved | |
| 08/21/2019 | STEM WALL/RETAINING WALL | RCHANDLER | Approved | |
| 08/21/2019 | EXCAVATION/LAYOUT REBAR & ZON | RCHANDLER | Approved | |
| 09/18/2019 | EXT METAL CLIPS/EXT SHEATHING | MRAMBER | Approved | |
| 09/30/2019 | ROOF NAILING | MRAMBER | Approved | |
| 10/04/2019 | PLUMBING - ABOVE CEILING | RCHANDLER | Approved | |
| 10/04/2019 | PLUMBING - INTERMEDIATE | RCHANDLER | Approved | Including gas test |
| 10/04/2019 | U VALUE FOR WINDOW | RCHANDLER | Approved | Glass in. Doors and corridor windows is not etched to identity as Tempered, one is cracked at this time and does not indicate that it is tempered. |
| 10/04/2019 | STUCCO MESH | RCHANDLER | Approved | |
| 10/11/2019 | ELECTRIC - ABOVE CEILING | RCHANDLER | Approved | |
| 10/11/2019 | PLUMBING - SEWER HCS CONNECT | RCHANDLER | Approved | |
| 10/11/2019 | MECHANICAL - ABOVE CEILING | RCHANDLER | Approved | |
| 10/11/2019 | PLUMBING - YARD WTR LINE/TEST | RCHANDLER | Approved | |
| 10/17/2019 | GAS CLEARANCE | RCHANDLER | Approved | |
| 11/04/2019 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | |
| 11/18/2019 | FRAMING | RCHANDLER | Approved | |
| 11/21/2019 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | |
| 11/29/2019 | ELECTRIC - UNDERGROUND | JCLAXTON | Approved | |
| 11/29/2019 | SHEET ROCK NAILING | JCLAXTON | Approved | |
| 11/29/2019 | FIREWALL/FIREBARRIER/FIRESTOP | JCLAXTON | Approved | 2nd layer hallway. |
| 12/20/2019 | TEP CLEARANCE - AM | MRAMBER | Approved | CODE ECO |
| 12/20/2019 | PLUMBING - GAS PRESSURE TEST | MRAMBER | Approved | Bonding to gas to be installed prior to clearance. |
| 12/20/2019 | ELECTRIC - CABLE DROP | MRAMBER | Approved | ECO OK to clear |
| 01/22/2020 | PLUMBING - GAS PRESS TEST FNL | WGALLAG1 | Approved | ok for clearance |
| 01/28/2020 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
| 02/10/2020 | RIGHT OF WAY - FINAL | MVV | Approved | No work in right-of-way. |
| 02/18/2020 | FIRE - FINAL | MRoss | Approved | |
| 02/18/2020 | FIRE - ALARM FINAL | MRoss | Approved | |
| 02/18/2020 | FIRE SPKLR - FINAL | MRoss | Approved | |
| 02/18/2020 | NPPO - FINAL | RLEDONNE | Approved | |
| 02/18/2020 | SIGN - FINAL | RLEDONNE | Approved | |
| 02/19/2020 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
| 02/25/2020 | ELECTRIC - FINAL | RCHANDLER | Approved | |
| 06/24/2020 | BUILDING - FINAL | CTREVI | Approved | |
| 06/24/2020 | LANDSCAPE - FINAL | CTREVI | Approved | REMAINING WORK TO BE COMPLETED WITH ACTIVITY T18CM09741 |
| 06/24/2020 | ENGINEERING - FINAL | CTREVI | Approved | REMAINING WORK TO BE COMPLETED WITH ACTIVITY T18CM09741 |