Permit: T18CM08767
Permit Details
Apply Date:
11/02/2018
Applicant:
MAHER, JOSEPH SAID JR
Description:
OFFICE
Architects:
- MAHER, JOSEPH SAID JR
Contractors:
- BARKER CONTRACTING INC **APA**
Permit Reviews
Permit Number - T18CM08767
Permit Status: C of o
Permit Description: OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/03/2020 | 3RD PARTY REVIEW - REVISION/OTHER-2ND | 01/08/2020 | ACTIVE |
03/06/2019 | POST 3RD PARTY REVIEW | 03/08/2019 | COMPLETED |
11/02/2018 | PLANS OK TO SUBMIT - COMM | 11/21/2018 | COMPLETED |
11/21/2018 | 3RD PARTY REVIEW - COMMERCIAL TI | 03/01/2019 | COMPLETED |
12/18/2019 | 3RD PARTY REVIEW - REVISION/OTHER | 01/02/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM08767
Permit Status: C of o
Permit Description: OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/02/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM08767
Permit Description: OFFICE
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/05/2019 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | ok to backfill. |
06/06/2019 | PLUMBING - PRE SLAB | AKLEINSORGE | Approved | Finish wrapping all pipe with foam wrap before placement of concrete |
06/27/2019 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | |
06/27/2019 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | |
06/27/2019 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | |
06/27/2019 | FRAMING | DMUNIZ | Approved | |
07/12/2019 | SHEET ROCK NAILING | AKLEINSORGE | Approved | Containment rooms, ok to fire stop and tape |
08/27/2019 | PLUMBING - ABOVE CEILING | DMUNIZ | Approved | |
09/05/2019 | MECHANICAL - ABOVE CEILING | DMUNIZ | Approved | Clean rooms and lockers ok to drop ceiling tiles. |
09/05/2019 | ELECTRIC - ABOVE CEILING | DMUNIZ | Approved | |
09/05/2019 | FIREWALL/FIREBARRIER/FIRESTOP | DMUNIZ | Approved | |
09/05/2019 | BUILDING ABOVE CEILING | DMUNIZ | Approved | |
12/11/2019 | FIRE - FINAL | MRoss | Approved | -Provide FDC Knox locking caps on FDCs on all buildings |
01/17/2020 | GAS CLEARANCE | DMUNIZ | Approved | |
01/17/2020 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | Clear Southwest Gas. |
07/31/2020 | MECHANICAL - FINAL | DMUNIZ | Approved | Approved |
07/31/2020 | PLUMBING - FINAL | DMUNIZ | Approved | Approved |
07/31/2020 | ELECTRIC - FINAL | DMUNIZ | Approved | Approved |
07/31/2020 | MECHANICAL - HOOD SYSTEMS | DMUNIZ | Approved | Approved |
07/31/2020 | MECHANICAL - HOODS | DMUNIZ | Approved | Approved |
07/31/2020 | PLUMBING - GAS PRESS TEST FNL | DMUNIZ | Approved | Approved |
08/03/2020 | FIRE SPKLR - FINAL | MRoss | Approved | |
08/03/2020 | NPPO - FINAL | RLEDONNE | Approved | Approved. |
08/03/2020 | SIGN - FINAL | RLEDONNE | Approved | Approved. |
08/03/2020 | LANDSCAPE - FINAL | RLEDONNE | Approved | Approved. |
08/03/2020 | ENGINEERING - FINAL | RLEDONNE | Approved | Approved. |
08/11/2020 | RIGHT OF WAY - FINAL | BMONG | Approved | ROW PERMIT WAS NOT ISSUED. NO INSPECTION WAS DONE BEFORE DRIVEWAYS WERE POURED. THEY DO MEET ADA LESS THAN 2% CROSS SLOPE. |
08/20/2020 | BUILDING - FINAL | TTREMBULAK | Approved | Approved |