Permit: T18CM08679
Permit Details
Status:
Final
Type:
SINGLE FAMILY ADDITION
Address:
42 E BILBY RD #01
Address NEW:
42 E BILBY RD #01
Apply Date:
10/30/2018
Applicant:
INAI ANZUETO - KRYSIL ENTERPRISES LLC
Description:
REMODELING INTERIOR & ENCLOSING CARPORT
Contractors:
- MARZO CONSTRUCTION INC
Permit Reviews
Permit Number - T18CM08679
Permit Status: Final
Permit Description: REMODELING INTERIOR & ENCLOSING CARPORT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/06/2019 | REVISION - - 1ST | 05/06/2019 | COMPLETED |
| 10/30/2018 | WALK THRU - RES | 12/11/2018 | COMPLETED |
| 12/11/2018 | RESUBMITTAL | 05/06/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM08679
Permit Status: Final
Permit Description: REMODELING INTERIOR & ENCLOSING CARPORT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/30/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM08679
Permit Description: REMODELING INTERIOR & ENCLOSING CARPORT
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/08/2019 | BUILDING PRE-SLAB | MHASSAN | Approved | |
| 02/08/2019 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | |
| 03/01/2019 | ROOF NAILING | MHASSAN | Approved | |
| 03/01/2019 | EXT METAL CLIPS/EXT SHEATHING | MHASSAN | Approved | |
| 03/13/2019 | TEP CLEARANCE - PM | RCAMACHO | Approved | CODE INCR |
| 04/01/2019 | PLUMBING - ROUGH, SOIL | RCHANDLER | Approved | Tie in to existing sewer line. |
| 05/08/2019 | PLUMBING - GAS PRESSURE TEST | MHASSAN | Approved | no gas in house |
| 05/08/2019 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | |
| 05/08/2019 | RESIDENTIAL INTERMEDIATE | MHASSAN | Approved | |
| 05/08/2019 | FRAMING | MHASSAN | Approved | |
| 05/08/2019 | PLUMBING - FINAL | MHASSAN | Approved | |
| 05/08/2019 | ELECTRIC - FINAL | MHASSAN | Approved | |
| 05/10/2019 | ZONING - FINAL | BBENEDON | Approved | |
| 05/10/2019 | MECHANICAL - FINAL | AKLEINSORGE | Approved | Drawings revised showing mechanical changes and all corrections completed. |
| 05/10/2019 | BUILDING - FINAL | AKLEINSORGE | Approved |