Permit: T18CM07845
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
2900 E ELVIRA RD BLD 2
Address NEW:
2900 E ELVIRA RD BLD 2
Apply Date:
10/03/2018
Applicant:
STEVE DAUGHERTY
Description:
New Building: Equipment Test Facility
Architects:
- SIBAYAN, RUBEN STANLEY
Contractors:
- KAPP CON INCORPORATED
Permit Reviews
Permit Number - T18CM07845
Permit Status: C of o
Permit Description: New Building: Equipment Test Facility
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/07/2019 | RESUBMITTAL | 01/25/2019 | COMPLETED |
| 01/25/2019 | RESUBMITTAL | 01/25/2019 | COMPLETED |
| 02/07/2019 | REVISION - - 1ST | 02/07/2019 | COMPLETED |
| 03/13/2019 | REVISION - - 2ND | 03/13/2019 | COMPLETED |
| 03/13/2019 | OTHER | 03/14/2019 | COMPLETED |
| 04/22/2019 | REVISION - - 3RD | 04/22/2019 | COMPLETED |
| 10/03/2018 | PLANS OK TO SUBMIT - COMM | 10/05/2018 | COMPLETED |
| 10/05/2018 | COMMERCIAL - NEW | 11/28/2018 | COMPLETED |
| 11/28/2018 | RESUBMITTAL | 12/26/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM07845
Permit Status: C of o
Permit Description: New Building: Equipment Test Facility
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/03/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM07845
Permit Description: New Building: Equipment Test Facility
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/11/2019 | ELECTRIC - UNDERGROUND | RCAMACHO | Approved | |
| 03/11/2019 | ELECTRIC - UFER | RCAMACHO | Approved | |
| 03/25/2019 | STEM WALL/RETAINING WALL | RCAMACHO | Approved | see RFI number 26 |
| 04/04/2019 | BUILDING PRE-SLAB | DQUINN | Approved | |
| 05/20/2019 | ROOF NAILING | MHASSAN | Approved | make sure to submit special inspection report on welding before end of job. |
| 05/21/2019 | REINFORCED MASONRY PRE-GROUT | RCAMACHO | Approved | |
| 05/24/2019 | FRAMING | RCAMACHO | Approved | |
| 05/28/2019 | ELECTRIC - PROGRESS | MHASSAN | Approved | approval is for rough in of interior walls |
| 07/17/2019 | EXCAVATION/LAYOUT REBAR & ZON | AKLEINSORGE | Approved | Exterior slab on grade along south side of building, ok for concrete placement |
| 08/19/2019 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | |
| 08/19/2019 | ELECTRIC - OUTDOOR LIGHTING | MHASSAN | Approved | |
| 08/19/2019 | ELECTRIC - INTERMEDIATE | MHASSAN | Approved | |
| 09/23/2019 | ENGINEERING - FINAL | BBENEDON | Approved | |
| 09/24/2019 | ELECTRIC - ABOVE CEILING | TVALENCIA | Approved | |
| 09/24/2019 | BUILDING ABOVE CEILING | TVALENCIA | Approved | 1- Mechanical above ceiling is okay. |
| 09/26/2019 | ELECTRIC - FINAL | TVALENCIA | Approved | |
| 09/26/2019 | OUTDOOR LIGHTING FINAL | TVALENCIA | Approved | |
| 09/26/2019 | BUILDING - PROGRESS | TVALENCIA | Approved | |
| 10/25/2019 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETE |
| 10/30/2019 | MECHANICAL - ABOVE CEILING | RSHERRY | Approved | |
| 11/13/2019 | FIRE - FINAL | CBASALDUA | Approved | |
| 11/13/2019 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 11/13/2019 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 11/14/2019 | BUILDING - FINAL | TVALENCIA | Approved |