Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Address Search: 2900 E ELVIRA RD
Search
Historic Records Requests
Address: 2900 E ELVIRA RD
Date - 11/24/2024 4:58 a.m.
Total Number Of Historic Records Requests - (1)
Name | Action |
---|---|
Address: 2900 E ELVIRA RD - Doc Type: CERT OF OCC |
Annexations & Original City Zoning (OCZ)
Address: 2900 E ELVIRA RD
Date - 11/24/2024 4:58 a.m.
Total Number Of Annexations & Original City Zoning (1)
Special Development Requests & Requirements
Address: 2900 E ELVIRA RD
Date - 11/24/2024 4:58 a.m.
Total Number Of Special Development Permits - (3)
Activity Number | Status | Apply Date | Expired Date | Unit | Type | Description |
---|---|---|---|---|---|---|
H000000719 | CLOSED | 08/12/2008 | N/A | Historical Information | ||
T08SA00360 | COMPLETE | 10/02/2008 | N/A | Zoning Adminstration Letter | ||
T13SA00367 | COMPLETE | 12/27/2013 | N/A | Zoning Adminstration Letter |
Permits
Address: 2900 E ELVIRA RD
Date - 11/24/2024 4:58 a.m.
Total Number Of Permits - (75)
Permit | Status | Apply Date | Expired Date | Unit | Type | Description |
---|---|---|---|---|---|---|
TC-COM-1223-02902 | Complete | 12/21/2023 | 05/12/2025 | Commercial Building | Adding additional electrical infrastructure and HVAC to existing building for future testing equipment. Adding a roll up door to the north end of the existing building. | |
T19CM07688 | Canceled | 10/18/2019 | N/A | Commercial Building | DRY ROOM EXPANSION - ELECTRICAL ONLY | |
T22RW03184 | Needs Resubmittal | 09/01/2022 | 01/09/2023 | Right-of-Way (ROW) | Starting on the South side of Elvira Rd East of South Tucson Blvd on TEP poles, Overlash .875 Coax g; Work Order: PRJ221107-1 | |
TF-FCP-0724-00568 | Issued | 07/16/2024 | 02/12/2025 | Fire Construction Permit | Replacement of an existing fire suppression system | |
T18OT00631 | Expired | 06/12/2018 | 12/09/2018 | Sign - Permanent | 2-non illum wall signs+ 1 CofC monu sign | |
DP18-0132 | Complete | 06/01/2018 | 03/21/2020 | Development Package | SITE/GRADE - SION POWER TEST EQUIPMENT BUILDING | |
T22FC00373 | Expired | 05/25/2022 | 07/15/2023 | Fire Construction Permit | Fire Alarm & Detection Systems - MODIFY AN EXISTING NEW FIKE CLEAN AGENT FIRE SUPPRESSION SYSTEM FOR SIONPOWER - TEST FACILITY - HEAT DETECTOR CHANGE.; Fire Alarm Systems - New Sq Ft: 4865; Fire Alarm Systems - # New Stories: 1 | |
T19FC00359 | Expired | 05/10/2019 | 11/26/2019 | Fire Construction Permit | Automatic Fire Extingshing Sys - Install One New Fike Clean Agent Fire Suppression system for Sion Power - Test Equipment TI; Special Hazard - New System: 1; Fire Alarm Systems - Devices Modified: 20 | |
TC-COM-0424-00720 | Inspections | 04/22/2024 | 05/20/2025 | Commercial Building | Adding a concrete pad to southeast side of existing building for new equipment. Added two new electrical connections to existing UPS for Sion Power at 2900 E. Elvira Road. | |
TC-COM-0424-00687 | Issued | 04/16/2024 | 11/06/2024 | BLDG 1 | Commercial Building | Replace 1-1/4" black iron pipe gas line, approx. 441 feet in length. Gas line runs on roof, down side of building. Gas line to new equipment will be 1" 5 psi gas system Total BTU 748k |
TR-UTL-0323-01147 | Complete | 03/22/2023 | 07/05/2023 | Right-of-Way (ROW) - Utility | PRJ221107-1 COX TO TRENCH 7' AND BORE 453' AND OVERLASH 969' FOR CATV CONDUIT FOR SYSTEM TIE. PREVIOUS PERMIT NUMBER T22RW03184. | |
TF-FCP-0323-00491 | Inspections | 03/21/2023 | 12/19/2023 | Fire Construction Permit | MODIFY THE EXISTING BUILDING FIRE ALARM SYSTEM | |
TC-COM-0323-00837 | Void | 03/20/2023 | 09/16/2023 | Commercial Building | VOIDED NEED TO APPLY FOR A Fire Alarm System Permit Modify the existing building fire alarm system | |
TC-COM-0324-00487 | Needs Resubmittal | 03/19/2024 | 09/15/2024 | BLDG 1 | Commercial Building | add concrete pad for equipment |
T19FC00071 | Expired | 01/28/2019 | 02/25/2020 | Fire Construction Permit | Automatic Fire Extingshing Sys - Install one new Fire clean agent Fire SUppression system for Sion Power; Special Hazard - New System: 1 | |
P00AN00268 | ISSUED | 01/26/2000 | N/A | ADDRNEW | ||
P98AN01738 | ISSUED | 07/15/1998 | N/A | #100 | ADDRNEW | |
P98AN01739 | ISSUED | 07/15/1998 | N/A | #150 | ADDRNEW | |
T00BU03139 | CLOSED | 10/20/2000 | 04/15/2008 | SPKLR | FIRE SPKR:16 NEW/60 FT OF 4'' UNDERGROUND FIRE SPKR PIPE | |
T00BU03325 | FINAL | 11/08/2000 | 06/12/2001 | #150 | SPKLR | FIRE:SPKR:42 NEW |
T00CM00354 | FINAL | 01/26/2000 | 05/15/2001 | COMBO | ADDITION:GARAGE | |
T00CM01577 | CLOSED | 03/28/2000 | 10/01/2000 | COMBO | TI:DEMOLISH CORRIDOR | |
T00CM01850 | CLOSED | 04/12/2000 | 10/11/2000 | COMBO | TI:OFFICE VESTIBULE INTERIOR DEMO | |
T00CM05282 | FINAL | 10/26/2000 | 06/12/2001 | #150 | COMBO | TI:OFFICE |
T00EL00136 | CLOSED | 01/18/2000 | 04/15/2008 | ELECT | ELECTRIC | |
T00EL02881 | WITHDRWN | 12/15/2000 | N/A | ELECT | ELECTRIC:COMPLIANCE | |
T01OT00146 | WITHDRWN | 05/25/2001 | N/A | SITE | SITE:PARKING LOT ONLY | |
T01OT00218 | CLOSED | 07/12/2001 | 12/31/2002 | REGPLANT | REGISTERED PLANT:2001 | |
T01OT01076 | FINAL | 12/12/2001 | 07/14/2002 | #100 | SIGN | SIGN:3430 |
T02BU02611 | FINAL | 10/03/2002 | 04/15/2003 | #150 | SPKLR | FIRE SPKR:RELOCATE 2 & ADD 6 |
T02CM04291 | WITHDRWN | 09/11/2002 | 04/30/2003 | COMBO | TI:OFFICE | |
T02OT01808 | FINAL | 11/20/2002 | 08/24/2003 | #150 | SIGN | SIGN:4755 |
T03BU00307 | FINAL | 02/05/2003 | 10/01/2003 | #150 | SPKLR | FIRE SPKR:ADD 4 |
T03OT00679 | CLOSED | 04/22/2003 | 12/31/2003 | #100 | REGPLANT | REGISTERED PLANT |
T04OT00419 | CLOSED | 03/01/2004 | 12/31/2004 | #100 | REGPLANT | REGISTERED PLANT |
T05BU02341 | WITHDRWN | 09/21/2005 | N/A | #150 | BUILD | TI:INTERIOR DEMO VAULT - DEQ# |
T07BU02253 | CLOSED | 10/25/2007 | 05/06/2008 | WALL/FEN | FENCE:1325LF OF 6' HIGH IRON & CHAINLINK | |
T07BU02421 | FINAL | 11/15/2007 | 08/30/2008 | SPKLR | Install 592 fire sprinklers | |
T07BU02492 | FINAL | 11/29/2007 | 09/14/2008 | BUILD | INSTALL CLEAN AGENT FIRE SUPPRESSION SYSTEM WITH ALARMS | |
T07BU02551 | FINAL | 12/07/2007 | 09/17/2008 | BUILD | NEW FIRE ALARM SYSTEM: REMODELED BUILDING | |
T07CM03323 | C OF O | 08/09/2007 | 09/14/2008 | #150 | COMBO | TI: FACTORY & OFFICE TCO FOR OFFICE STAFF |
T07EX01296 | CLOSED | 12/31/2007 | 02/29/2008 | EXCAV | 13 LF OF TRENCH | |
T07OT02919 | FINAL | 12/27/2007 | 08/06/2008 | #100 | SIGN | 14238 |
T08EX00106 | CLOSED | 02/01/2008 | 04/01/2008 | EXCAV | EXCAVATION OF 40' IN PAVEMENT FOR GASLINE THT WILL | |
T09BU00392 | FINAL | 03/17/2009 | 03/01/2010 | BUILD | CLEAN AGENT FIRE SUPPRESSION SYSTEM | |
T09CM02157 | WITHDRWN | 08/11/2009 | N/A | COMBO | INSTALL: | |
T10CM01978 | EXPIRED | 07/16/2010 | 04/18/2011 | #100 | COMBO | ADD GENERATOR & CONCRETE PAD |
T12CM07920 | FINAL | 12/14/2012 | 09/07/2013 | COMBO | REPLACE CHILLER MECHANICAL UPGRADES | |
T13BU00578 | FINAL | 05/16/2013 | 01/15/2014 | #100 | SPKLR | REPLACE CLEAN AGENT SYSTEM |
T18BU00592 | FINAL | 10/19/2018 | 05/15/2019 | DEMO | DEMO OF METAL STORAGE | |
T18CM07845 | C OF O | 10/03/2018 | 05/12/2020 | BLD 2 | COMBO | New Building: Equipment Test Facility |
T18CM07852 | EXPIRED | 10/03/2018 | 12/09/2019 | BLD 1 | COMBO | TI: EQUIPMENT TEST |
T18FC00270 | WITHDRWN | 04/03/2018 | 04/09/2019 | FIRECONS | PANEL REPLACEMENT. 11/17/21 After being told we were getting the job and thus us getting the permit, Sion Power had American Fire do the project. - Jennifer Peel-Davis asked me to withdraw permit. | |
T20CM07360 | FINAL | 10/27/2020 | 10/09/2021 | BLD 2 | COMBO | TI: CONVERSION OF EXISTING S-1 OCC TO H-2 OCC |
T20FC00752 | FINAL | 11/04/2020 | 10/04/2021 | FIRECONS | MODIFY ONE (1) NEW FIKE CLEAN AGENT FIRE SUPPRESSION SYSTEM FOR SION POWER NEW BATTERY ROOM. | |
T21FC00481 | FINAL | 06/15/2021 | 02/13/2022 | FIRECONS | Add a new Fire suppression system to an existing Notifier panel | |
T97BU01177 | FINAL | 06/25/1997 | 02/02/1998 | SPKLR | FIRE SPKR:ADD 402 | |
T97BU01762 | FINAL | 09/02/1997 | 10/20/1998 | SPKLR | FIRE SPKR:ADD 4 | |
T97BU01763 | FINAL | 09/02/1997 | 10/20/1998 | SPKLR | FIRE SPKR:ADD 8 | |
T97CM00717 | WITHDRWN | 04/07/1997 | N/A | COMBO | TENANT IMPROVEMENT:OFFICE | |
T97CM00797 | C OF O | 04/10/1997 | 02/24/1998 | COMBO | TI:OFFICE/MANUFACTURING | |
T97OT00144 | EXPIRED | 07/29/1997 | 12/31/1998 | REGPLANT | REGISTERED PLANT FOR: H E MICROWAVE | |
T97PL01184 | CLOSED | 08/21/1997 | 04/15/2008 | PLUMB | GAS LINE:RECONNECT | |
T98BU01674 | FINAL | 07/06/1998 | 03/23/1999 | #150 | BUILD | HANDICAP RAMP |
T98BU01741 | FINAL | 07/14/1998 | 04/05/1999 | #150 | SPKLR | FIRE SPKR:ADD 283 & RELOC 7 |
T98BU02310 | FINAL | 09/21/1998 | 04/05/1999 | #150 | SPKLR | FIRE SPKR:ADD 15 |
T98CM02695 | WITHDRWN | 06/19/1998 | N/A | #100 | COMBO | ADDITION:GARAGE & PARKING LOT |
T98CM02841 | C OF O | 06/29/1998 | 04/12/1999 | #150 | COMBO | TI:OFFICE DEFERRED SUBMITTAL |
T98EL01189 | FINAL | 07/01/1998 | 04/12/1999 | #150 | ELECT | ELECTRIC: DEFERRED SUBMITTAL |
T98EX01428 | CLOSED | 11/25/1998 | 01/24/1999 | EXCAV | EXCAV:TRENCH FOR VAULT | |
T98PL01372 | FINAL | 06/25/1998 | 04/12/1999 | #150 | PLUMB | PLUMBING:ROUGH:DEFERRED SUBMITTAL |
T99BU01261 | FINAL | 05/10/1999 | 11/14/1999 | #150 | SPKLR | FIRE SPKR:NEW 7 |
T99BU03476 | FINAL | 12/27/1999 | 06/27/2000 | #150 | SPKLR | FIRE SPKR:ADD 2 RELOCATE 4 |
T99CM01753 | C OF O | 04/14/1999 | 11/22/1999 | #150 | COMBO | TI:OFFICE |
T99CM05625 | FINAL | 12/01/1999 | 07/19/2000 | #302 | COMBO | TI:OFFICE |
Plans
Address: 2900 E ELVIRA RD
Date - 11/24/2024 4:58 a.m.
Total Number Of Plans - (1)
Plan Number | Status | Application Date | Exp Date | Unit | Type | Description |
---|---|---|---|---|---|---|
T05BA00531 | Approved | 11/30/2005 | N/A | -- Stormwater Basin |
Record Requests
Address: 2900 E ELVIRA RD
Date - 11/24/2024 4:58 a.m.
Total Number Of Requests - (2)
Request Number | Status | Request Date | Completed Date | Type | Description |
---|---|---|---|---|---|
REQ-1124-07769 | Denied | 11/15/2024 | N/A | Requests | This Project is not complete all related permits need to be in completed status TF-FCP-0323-00491. Please re-request once all associated projects are in completed status. Adding additional electrical infrastructure and HVAC to existing building for future testing equipment. Adding a roll up door to the north end of the existing building. |
REQ-1124-07922 | Complete | 11/19/2024 | 11/20/2024 | Requests | Adding additional electrical infrastructure and HVAC to existing building for future testing equipment. Adding a roll up door to the north end of the existing building. |