Permit: T18CM07703
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
4811 E GRANT RD #119
Address NEW:
4811 E GRANT RD #119
Apply Date:
09/27/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI: CALL CENTER
Contractors:
- MENEMSHA DEVELOPMENT GROUP INC ,
Permit Reviews
Permit Number - T18CM07703
Permit Status: C of o
Permit Description: TI: CALL CENTER
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/27/2018 | COMMERCIAL - TI | 10/26/2018 | COMPLETED |
| 10/10/2018 | RESUBMITTAL | 10/26/2018 | COMPLETED |
| 10/26/2018 | RESUBMITTAL | 10/26/2018 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T18CM07703
Permit Status: C of o
Permit Description: TI: CALL CENTER
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/27/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM07703
Permit Description: TI: CALL CENTER
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/14/2018 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | |
| 11/14/2018 | FRAMING | RCHANDLER | Approved | |
| 11/15/2018 | MECHANICAL - ABOVE CEILING | DMCCARTHY | Approved | STILL NEED EL ROUGH INSP (AKA INTERMEDIATE). |
| 11/15/2018 | PLUMBING - INTERMEDIATE | DMCCARTHY | Approved | |
| 11/15/2018 | PLUMBING - ROUGH, SOIL | DMCCARTHY | Approved | SMALL TENENT IMPROVEMENT |
| 11/19/2018 | ELECTRIC - ABOVE CEILING | DMCCARTHY | Approved | |
| 11/19/2018 | ELECTRIC - INTERMEDIATE | DMCCARTHY | Approved | |
| 11/30/2018 | FIRE - FINAL | gsereno1 | Approved | |
| 11/30/2018 | FIRE SPKLR - FINAL | gsereno1 | Approved | |
| 11/30/2018 | FIRE - ALARM FINAL | gsereno1 | Approved | |
| 12/10/2018 | PLUMBING - PROGRESS | GWEST | Approved | |
| 12/10/2018 | CERTIFICATE OF OCCUPANCY | GWEST | Approved | |
| 12/10/2018 | ELECTRIC - FINAL | GWEST | Approved | |
| 12/10/2018 | BUILDING - FINAL | GWEST | Approved | |
| 12/10/2018 | BUILDING ABOVE CEILING | GWEST | Approved | |
| 12/10/2018 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 12/12/2018 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
| 12/12/2018 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER CHLORINATION REPORT COMPLETED |