Permit: T18CM07668
Permit Details
Status:
Final
Type:
SINGLE FAMILY NEW
Address:
7233 S PASEO MONTE DE ORO
Address NEW:
7233 S PASEO MONTE DE ORO
Apply Date:
09/26/2018
Applicant:
RICHMOND AMERICAN HOMES ** APA ***
Description:
SFR RICHT91718 T18-M0024
Contractors:
- RICHMOND AMERICAN CONSTRUCTION INC
Permit Reviews
Permit Number - T18CM07668
Permit Status: Final
Permit Description: SFR RICHT91718 T18-M0024
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/26/2018 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 09/26/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM07668
Permit Status: Final
Permit Description: SFR RICHT91718 T18-M0024
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/26/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM07668
Permit Description: SFR RICHT91718 T18-M0024
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/09/2018 | PLUMBING - SEWER HCS CONNECT | TVALENCIA | Approved | |
| 10/09/2018 | PLUMBING - YARD WTR LINE/TEST | TVALENCIA | Approved | |
| 10/11/2018 | PLUMBING - ROUGH, SOIL | TVALENCIA | Approved | |
| 10/17/2018 | ELECTRIC - UNDERGROUND | TVALENCIA | Approved | |
| 10/17/2018 | BUILDING PRE-SLAB | TVALENCIA | Approved | |
| 10/17/2018 | EXCAVATION/LAYOUT REBAR & ZON | TVALENCIA | Approved | |
| 10/31/2018 | ROOF NAILING | TVALENCIA | Approved | |
| 11/02/2018 | EXT METAL CLIPS/EXT SHEATHING | GWEST | Approved | |
| 12/03/2018 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 12/03/2018 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | |
| 12/03/2018 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 12/03/2018 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | |
| 12/03/2018 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
| 12/03/2018 | ELECTRIC - UFER | DQUINN | Approved | |
| 12/03/2018 | FRAMING | DQUINN | Approved | |
| 12/04/2018 | TEP CLEARANCE - AM | DQUINN | Approved | ECO |
| 12/19/2018 | SHEET ROCK NAILING | DMUNIZ | Approved | |
| 01/23/2019 | GAS CLEARANCE | DMUNIZ | Approved | |
| 01/25/2019 | MECHANICAL - FINAL | DMUNIZ | Approved | |
| 01/25/2019 | PLUMBING - FINAL | DMUNIZ | Approved | |
| 01/25/2019 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
| 01/28/2019 | ELECTRIC - FINAL | DMUNIZ | Approved | |
| 01/28/2019 | BUILDING - FINAL | DMUNIZ | Approved |