Permit: T18CM07570
Permit Details
Apply Date:
09/24/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
SHELL BUILDING
Architects:
- JOHNSTON, TIMOTHY
Contractors:
- 7B BUILDING + DEVELOPMENT LLC
Permit Reviews
Permit Number - T18CM07570
Permit Status: L of c
Permit Description: SHELL BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/22/2019 | RESUBMITTAL | 01/25/2019 | COMPLETED |
| 01/30/2019 | OTHER | 02/28/2019 | COMPLETED |
| 09/24/2018 | PLANS OK TO SUBMIT - COMM | 10/03/2018 | COMPLETED |
| 09/24/2018 | COMMERCIAL - TI | 12/04/2018 | COMPLETED |
| 12/04/2018 | COMMERCIAL - TI | 01/22/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM07570
Permit Status: L of c
Permit Description: SHELL BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/24/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T18CM07570
Permit Description: SHELL BUILDING
Total Completed Inspections - 47
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/08/2019 | PLUMBING - ROUGH, SOIL | RCAMACHO | Approved | |
| 03/11/2019 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | install third horizontal rebar in south west corner of footing per plan. Clean out footings before pour |
| 03/11/2019 | PLUMBING - PRE SLAB | MHASSAN | Approved | |
| 03/11/2019 | PLUMBING - BACK WATER VALVE | MHASSAN | Approved | |
| 03/21/2019 | ELECTRIC - UFER | MHASSAN | Approved | |
| 03/21/2019 | SITE - SEWER | MHASSAN | Approved | |
| 03/21/2019 | PLUMBING - SEWER HCS CONNECT | MHASSAN | Approved | |
| 04/02/2019 | ELECTRIC - UNDERGROUND | RCAMACHO | Approved | |
| 04/03/2019 | PLUMBING - YARD WTR LINE/TEST | MHASSAN | Approved | keep pictures after copper is installed trench depth is good |
| 04/03/2019 | EXT METAL CLIPS/EXT SHEATHING | MHASSAN | Approved | |
| 04/11/2019 | PLUMBING - PROGRESS | RCAMACHO | Approved | |
| 04/11/2019 | ELECTRIC - PROGRESS | RCAMACHO | Approved | |
| 04/11/2019 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | |
| 04/11/2019 | FRAMING | RCAMACHO | Approved | |
| 04/12/2019 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | |
| 04/17/2019 | SHEET ROCK NAILING | RCAMACHO | Approved | |
| 04/22/2019 | ELECTRIC - CONSTRUCTION POWER | RCAMACHO | Approved | for test ECO To remain locked out tagged out |
| 04/25/2019 | TEP CLEARANCE - PM | RCHANDLER | Approved | RE SEND ECO |
| 04/26/2019 | GAS CLEARANCE | MHASSAN | Approved | |
| 04/26/2019 | PLUMBING - GAS PRESSURE TEST | MHASSAN | Approved | OK to clear gas for new service |
| 05/13/2019 | PLUMBING - ABOVE CEILING | RCAMACHO | Approved | |
| 05/13/2019 | ELECTRIC - ABOVE CEILING | RCAMACHO | Approved | |
| 05/13/2019 | BUILDING ABOVE CEILING | RCAMACHO | Approved | |
| 05/22/2019 | MECHANICAL - ABOVE CEILING | RCAMACHO | Approved | |
| 05/22/2019 | REINFORCED MASONRY PRE-GROUT | RCAMACHO | Approved | |
| 06/11/2019 | OUTDOOR LIGHTING FINAL | MHASSAN | Approved | APPROVED PER 2090 APPROVAL |
| 06/11/2019 | ELECTRIC - OUTDOOR LIGHTING | MHASSAN | Approved | PPROVED PER 2090 APPROVAL |
| 06/11/2019 | PLUMBING - GAS PRESS TEST FNL | MHASSAN | Approved | |
| 06/11/2019 | U VALUE FOR WINDOW | MHASSAN | Approved | |
| 06/11/2019 | STUCCO MESH | MHASSAN | Approved | |
| 06/11/2019 | BUILDING PRE-SLAB | MHASSAN | Approved | |
| 06/11/2019 | ELECTRIC - FINAL | MHASSAN | Approved | |
| 06/11/2019 | PLUMBING - FINAL | MHASSAN | Approved | |
| 06/11/2019 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
| 06/24/2019 | FIRE - FINAL | CBASALDUA | Approved | |
| 06/24/2019 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | |
| 07/03/2019 | MECHANICAL - FINAL | MHASSAN | Approved | |
| 07/03/2019 | MECHANICAL - PROGRESS | MHASSAN | Approved | |
| 07/03/2019 | MECHANICAL - PROGRESS | MHASSAN | Approved | |
| 07/03/2019 | ELECTRIC - SERVICE UPGRADE | MHASSAN | Approved | |
| 07/03/2019 | ELECTRIC - SERVICE UPGRADE | MHASSAN | Approved | |
| 07/03/2019 | FIREWALL/FIREBARRIER/FIRESTOP | MHASSAN | Approved | |
| 07/03/2019 | FIREWALL/FIREBARRIER/FIRESTOP | MHASSAN | Approved | |
| 07/03/2019 | ROOF NAILING | MHASSAN | Approved | |
| 07/03/2019 | ROOF NAILING | MHASSAN | Approved | |
| 07/10/2019 | BUILDING - FINAL | MHASSAN | Approved | ALL INSPECTIONS COMPLETED AND CERTIFICATES TURNED IN. DEBRIS CLEARED. (OK'S PER PHONE CONVERSATION WITH MIKE HASSAN) |
| 07/10/2019 | ENGINEERING - FINAL | DROBERTS | Approved | THE ENGINEER OF RECORD JONATHAN D BURKHARDT PROVIDED THIS DEPARTMENT WITH A CERTIFICATION FOR THIS PROJECT ON 7/8/2019 THAT IS SEALED, STATING THAT ALL OF THE WORK WAS COMPLETED PER THE APPROVED EVEN THOUGH NOE OF THE WORK WAS INSPECTED BY THIS DEPARTMENT DURING THE CONSTRUCTION. |