Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Expired
Type:
Commercial Building
Apply Date:
09/24/2018
Applicant:
Description:
TI: OFFICE

Permit Reviews

Permit Number - T18CM07565
Permit Status: Expired
Permit Description: TI: OFFICE
Start Date Submittal Complete Date Status  
09/24/2018 COMMERCIAL - TI 09/25/2018 COMPLETED Review Details
09/25/2018 COMMERCIAL - TI 10/01/2018 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM07565
Permit Status: Expired
Permit Description: TI: OFFICE
Total Outstanding Activity Conditions - 1
Date Name
09/24/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Outstanding Inspections

Permit Status: Expired
Permit Number: T18CM07565
Permite Description: TI: OFFICE
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
08/21/2019 COT - LCBU - Framing N/A Canceled {Activity date: 08/21/2019; Status: Not Applicable; Inspector: DQUINN; Comment: Entered by DMERANZ1 - }

Completed Inspections

Permit Status: Expired
Permit Number: T18CM07565
Permit Description: TI: OFFICE
Total Completed Inspections - 14
Date Description Inspector Results Comments
12/21/2018 COT - LCBU - Building Above Ceiling Passed {Activity date: 12/21/2018; Status: Approved; Inspector: TVALENCIA; Comment: Entered by CBELL1 - }
12/21/2018 COT - LCEL - Electrical Intermediate Passed {Activity date: 12/21/2018; Status: Approved; Inspector: TVALENCIA; Comment: Entered by CBELL1 - }
12/21/2018 COT - LCPL - Plumbing Intermediate Passed {Activity date: 12/21/2018; Status: Approved; Inspector: TVALENCIA; Comment: Entered by CBELL1 - }
12/21/2018 COT - LCPL - Rough Soil Passed {Activity date: 12/21/2018; Status: Approved; Inspector: TVALENCIA; Comment: Entered by CBELL1 - }
12/21/2018 COT - LCEL - Electrical Above Ceiling Passed {Activity date: 12/21/2018; Status: Approved; Inspector: TVALENCIA; Comment: Entered by CBELL1 - }
12/21/2018 COT - LCBU - Building Progress Passed {Activity date: 12/21/2018; Status: Approved; Inspector: TVALENCIA; Comment: Entered by CBELL1 - }
01/03/2019 COT - LCME - Mechanical Intermediate Passed {Activity date: 01/03/2019; Status: Approved; Inspector: TVALENCIA; Comment: Entered by CBELL1 - }
01/15/2019 COT - LCME - Mechanical Above Ceiling Passed {Activity date: 01/15/2019; Status: Approved; Inspector: TVALENCIA; Comment: Entered by CBELL1 - } ; {Activity date: 01/03/2019; Status: Partial Approval; Inspector: TVALENCIA; Comment: Entered by CBELL1 - 1- Supply and Return flex duct is okay for ceiling grid.}
02/08/2019 COT - LCEL - Electrical Final Passed {Activity date: 02/08/2019; Status: Approved; Inspector: TVALENCIA; Comment: Entered by CBELL1 - }
02/11/2019 COT - LCME - Mechanical Final Passed {Activity date: 02/11/2019; Status: Approved; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - REVIEW OF AIR BALANCE REPORT COMPLETED} ; {Activity date: 02/08/2019; Status: Partial Approval; Inspector: TVALENCIA; Comment: Entered by CBELL1 - } ; {Activity date: 09/27/2018; Status: Prior to Final Inspectn; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - AIR BALANCE REPORT REQUIRED}
02/11/2019 COT - LCPL - Plumbing Final Passed {Activity date: 02/11/2019; Status: Approved; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - REVIEW OF WATER CHLORINATION REPORT COMPLETED.} ; {Activity date: 02/08/2019; Status: Partial Approval; Inspector: TVALENCIA; Comment: Entered by CBELL1 - } ; {Activity date: 09/25/2018; Status: Prior to Final Inspectn; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - WATER CHLORINATION REPORT REQUIRED}
03/15/2019 COT - FCON - Fire - Final Passed {Activity date: 03/15/2019; Status: Approved; Inspector: CBASALDUA; Comment: Entered by CBASALD1 - } ; {Activity date: 02/08/2019; Status: Denied; Inspector: jvincent; Comment: Entered by JVINCEN1 - 1. repair sprinkler heads. some are bent. some are too low below the tiles or too high.
2. provide key for knox box.
3. annual and 5yr inspection report for fire alarm.
4. annual inspection report for fire alarm.
5. AES radio was not permitted. replace with cellular dialer and phone line.
6. power strip set up next to fire alarm panel for transformer needs to be corrected and locked.
7. suite number rear doors.
8. flush FDC's, AHJ to witness.
9. add supports to arm overs that were added.
10. knox FDC plugs needed after flush. Have on site during flush so we can install immediatley after flush.
11. mount extinguishers.

Contact: Jay Post 310-1611}
08/21/2019 COT - LCBU - Building Final Passed {Activity date: 08/21/2019; Status: Approved; Inspector: DQUINN; Comment: Entered by DMERANZ1 - Note: the address on the permit was the contractors address. The site address is 3700 n 1st ave. # 2021} ; {Activity date: 02/08/2019; Status: Partial Approval; Inspector: TVALENCIA; Comment: Entered by CBELL1 - 1- Bldg. final is okay for C of O pending Fire inspection,air balance and water chlorination report approval}
08/21/2019 ENGR Engineering Final Passed {Activity date: 08/21/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - This inspection is actually 3700 N. 1st Ave., Apt. 2021.}

Documents

File Name Document Type  
001_T0.0.TIF CONSTRPLANS VIEW
002_T1.0.TIF CONSTRPLANS VIEW
003_D1.0.TIF CONSTRPLANS VIEW
004_A1.0.TIF CONSTRPLANS VIEW
005_A1.1.TIF CONSTRPLANS VIEW
006_A3.0.TIF CONSTRPLANS VIEW
007_A5.0.TIF CONSTRPLANS VIEW
008_A12.0.TIF CONSTRPLANS VIEW
009_A15.0.TIF CONSTRPLANS VIEW
010_M0.0.TIF CONSTRPLANS VIEW
011_M1.0.TIF CONSTRPLANS VIEW
012_P0.0.TIF CONSTRPLANS VIEW
013_P1.0.TIF CONSTRPLANS VIEW
014_E0.0.TIF CONSTRPLANS VIEW
015_E1.1.TIF CONSTRPLANS VIEW
016_E2.1.TIF CONSTRPLANS VIEW
None DOCUMENTS VIEW
T18CM07565 AIR BALANCE.PDF DOCUMENTS VIEW
None DOCUMENTS VIEW