Permit: T18CM06723
Permit Details
Apply Date:
08/24/2018
Applicant:
N/A
Description:
ELECTRICAL UPGRADE & NEW HVAC
Architects:
- JAKE BOEN
Contractors:
- LETS DO IT LLC
Permit Reviews
Permit Number - T18CM06723
Permit Status: Final
Permit Description: ELECTRICAL UPGRADE & NEW HVAC
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/24/2018 | WALK THRU - COMM | 10/05/2018 | COMPLETED |
| 10/16/2018 | OTHER | 10/29/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM06723
Permit Status: Final
Permit Description: ELECTRICAL UPGRADE & NEW HVAC
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/24/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM06723
Permit Description: ELECTRICAL UPGRADE & NEW HVAC
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/30/2018 | ELECTRIC - ABOVE CEILING | BSTEVENS | Approved | Some bathroom fans not wired, some conduit is terminated without bushing. |
| 10/30/2018 | ELECTRIC - INTERMEDIATE | BSTEVENS | Approved | Ungrounded metal electrical boxes, vent fans in restrooms not wired, some conduit is not secured to wall. |
| 12/19/2018 | ELECTRIC - SERVICE UPGRADE | ESTEVENS | Approved | New 400 amp panel. The TEP code is INCR. |
| 12/20/2018 | TEP CLEARANCE - AM | ESTEVENS | Approved | INCR |
| 01/23/2019 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | |
| 01/23/2019 | BUILDING ABOVE CEILING | ESTEVENS | Approved | |
| 01/23/2019 | FRAMING | ESTEVENS | Approved | |
| 01/23/2019 | REINFORCED MASONRY PRE-GROUT | ESTEVENS | Approved | |
| 02/04/2019 | OUTDOOR LIGHTING FINAL | TVALENCIA | Approved | |
| 02/04/2019 | ELECTRIC - OUTDOOR LIGHTING | TVALENCIA | Approved | |
| 02/04/2019 | ELECTRIC - FINAL | TVALENCIA | Approved | |
| 02/04/2019 | MECHANICAL - FINAL | TVALENCIA | Approved | units 02, 03, 04, 05, 06, 07, 08 only |
| 02/04/2019 | BUILDING - FINAL | TVALENCIA | Approved | |
| 02/05/2019 | GAS CLEARANCE | TVALENCIA | Approved |