Permit Details

Status:
Expired
Type:
Commercial Building
Apply Date:
08/14/2018
Applicant:
Description:
NEW POWER PLANT

Permit Reviews

Permit Number - T18CM06337
Permit Status: Expired
Permit Description: NEW POWER PLANT
Start Date Submittal Complete Date Status  
08/14/2018 PLANS OK TO SUBMIT - COMM 08/14/2018 COMPLETED Review Details
08/14/2018 COMMERCIAL - NEW 08/29/2018 COMPLETED Review Details
09/04/2018 RESUBMITTAL 10/02/2018 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM06337
Permit Status: Expired
Permit Description: NEW POWER PLANT
Total Outstanding Activity Conditions - 1
Date Name
08/14/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Expired
Permit Number: T18CM06337
Permit Description: NEW POWER PLANT
Total Completed Inspections - 13
Date Description Inspector Results Comments
12/20/2018 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 12/20/2018; Status: Approved; Inspector: BJONES; Comment: Entered by CBELL1 - Steel per engineer details
Rebar double Matt #4 Footings #6 12"EW
Matt’s are 8"EW at Ends to 12" EW at Interior per plan
Grounding Electrode Conductors are Cad Welded to rebar
Conduits per specifications and secured in place. Conduits are with steel nipples through concrete.
Special Inspecton by Others}
12/09/2019 TRSP - ROW - Final/Close-Out Passed {Activity date: 12/09/2019; Status: Approved; Inspector: B Mong; Comment: Entered by MBRAVIN1 - No ROW issues}
08/11/2020 COT - LCBU - Building Above Ceiling Passed {Activity date: 08/11/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by JSCHNEI2 - Approved}
08/11/2020 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 08/11/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Approved.} ; {Activity date: 12/09/2019; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - complete development package noted on engineer in final for landscape final.

}
08/11/2020 COT - LCBU - Building Final Passed {Activity date: 08/11/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by JSCHNEI2 - Approved} ; {Activity date: 12/09/2019; Status: Not ready for Inspection; Inspector: JCLAXTON; Comment: Entered by DMERANZ1 - Complete bathroom.
Need permanent labels for all panel.
Need to label all breakers.
Install required emergency lights and exit lights.
Complete mechanical.
Need engineering and fire finals.} ; {Activity date: 12/04/2019; Status: Cancelled; Inspector: JCLAXTON; Comment: Entered by SFLORES2 - }
08/11/2020 COT - LCBU - Framing Passed {Activity date: 08/11/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by JSCHNEI2 - Approved} ; {Activity date: 02/26/2019; Status: Partial Approval; Inspector: BJONES; Comment: Entered by CBELL1 - Walked frame with Bill Roberson, Project Superintendent. All bolting tight, bracing where required by engineered plan specifications. Inspection by 3rd party and TEP QC}
08/11/2020 COT - LCBU - Preslab Passed {Activity date: 08/11/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by JSCHNEI2 - Approved}
08/11/2020 COT - LCBU - Roof Nailing Passed {Activity date: 08/11/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by JSCHNEI2 - Approved}
08/11/2020 COT - LCBU - Building Progress Passed {Activity date: 08/11/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by JSCHNEI2 - Approved} ; {Activity date: 12/04/2019; Status: Partial Approval; Inspector: JCLAXTON; Comment: Entered by SFLORES2 - Discussed what is needed for finals for bldgs} ; {Activity date: 09/05/2019; Status: Not ready for Inspection; Inspector: DQUINN; Comment: Entered by DMERANZ1 - Pre final mtg
}
08/13/2020 COT - FCON - Alarm - Final Passed {Activity date: 08/13/2020; Status: Approved; Inspector: jfordney; Comment: Entered by JFORDNE1 - } ; {Activity date: 08/11/2020; Status: Partial Approval; Inspector: jfordney; Comment: Entered by JFORDNE1 - see t18cm05882}
08/13/2020 COT - FCON - Sprinkler - Final Passed {Activity date: 08/13/2020; Status: Approved; Inspector: jfordney; Comment: Entered by JFORDNE1 - } ; {Activity date: 08/11/2020; Status: Partial Approval; Inspector: jfordney; Comment: Entered by JFORDNE1 - see t18cm05882}
08/13/2020 COT - FCON - Fire - Final Passed {Activity date: 08/13/2020; Status: Approved; Inspector: jfordney; Comment: Entered by JFORDNE1 - } ; {Activity date: 08/11/2020; Status: Partial Approval; Inspector: jfordney; Comment: Entered by JFORDNE1 - see t18cm05882}
04/01/2022 ENGR Engineering Final Passed {Activity date: 04/01/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 08/11/2020; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Not ready. Complete all work and notes on development packages for this project for engineering final.} ; {Activity date: 12/09/2019; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Development package DP17-0267. Must be complete before signing off this permit.}