Permit: T18CM06028
Permit Details
Apply Date:
08/03/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
SHELL BLDG
Architects:
- GARCIA DAVID V
Contractors:
- RENAISSANCE COMPANIES , THE
Permit Reviews
Permit Number - T18CM06028
Permit Status: Final
Permit Description: SHELL BLDG
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/03/2018 | PLANS OK TO SUBMIT - COMM | 08/03/2018 | COMPLETED |
08/03/2018 | 3RD PARTY REVIEW - COMMERCIAL | 09/11/2018 | COMPLETED |
09/11/2018 | POST 3RD PARTY REVIEW | 09/21/2018 | COMPLETED |
10/10/2018 | REVISION - - 1ST | 10/10/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM06028
Permit Status: Final
Permit Description: SHELL BLDG
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/03/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM06028
Permit Description: SHELL BLDG
Total Completed Inspections - 38
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/20/2018 | PLUMBING - FINAL | GKOZIOL | Approved | ISSUED WITH CONDITIONS: NO PHYSICAL CONNECTION TO THE PUBLIC SEWER UNTIL THE PUBLIC SEWER G-2018-069 IS ACCEPTED AND RELEASED BY PCRWRD NO FINAL AND NO CERTIFICATE OF OCCUPANCY UNTIL THE DISCHARGE AUTHORIZATION(D.A.) IS ISSUED FOR G-2018-069 BY PCDSD NO FINAL AND NO CERTIFICATE OF OCCUPANCY UNTIL THE PUBLIC SEWER G-2018-069 IS ACCEPTED AND RELEASED BY PCRWRD ADDITIONAL CONDITION: THE PUBLIC SEWER G-2018-069 IS NOT APPROVED AS YET BY PCDSD THE OWNER ASSUMES THE RISK FOR ANY CHANGES TO THE PUBLIC SEWER THAT AFFECT THE GEICO BUILDING CONNECTION SEWER (BCS-PRIVATE SEWER) |
10/30/2018 | BUILDING PRE-SLAB | RCAMACHO | Approved | After-hours inspection APA account $165 Switchgear pad southeast of substation half of pad only East half 16 foot |
10/30/2018 | ELECTRIC - TEMPORARY SERVICE | RCAMACHO | Approved | |
12/06/2018 | ELECTRIC - UNDERGROUND | RCHANDLER | Approved | West side conduit for parking lot lights. South side conduits for middle row of parking lot lights. |
12/06/2018 | EXCAVATION/LAYOUT REBAR & ZON | RCHANDLER | Approved | Complete building. |
12/11/2018 | PLUMBING - PRE SLAB | DMCCARTHY | Approved | plumbing pre-slab for water supply and roof drain inside previously poured floor for tilt up new |
12/27/2018 | ELECTRIC - OUTDOOR LIGHTING | RCHANDLER | Approved | Light poles SW parking lot. |
04/10/2019 | PLUMBING - MD GAS/PRECONST MTG | MHASSAN | Approved | building has no med gas |
07/18/2019 | ELECTRIC - CONSTRUCTION POWER | MHASSAN | Approved | |
07/18/2019 | MECHANICAL - ABOVE CEILING | MHASSAN | Approved | MISSING INSPECTIONS SHOULD BE UNDER TI PERMIT |
07/18/2019 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | |
07/18/2019 | SITE - SEWER | MHASSAN | Approved | |
07/18/2019 | PLUMBING - SEWER HCS CONNECT | MHASSAN | Approved | |
07/18/2019 | PLUMBING - ROOF DRAINS | MHASSAN | Approved | MISSING INSPECTIONS SHOULD BE UNDER FOUNDATION OR TI PERMITS |
07/18/2019 | PLUMBING - ABOVE CEILING | MHASSAN | Approved | |
07/18/2019 | PLUMBING - INTERMEDIATE | MHASSAN | Approved | MISSING INSPECTIONS SHOULD BE UNDER THE TI |
07/18/2019 | PLUMBING - ROUGH, SOIL | MHASSAN | Approved | |
07/18/2019 | ELECTRIC - CABLE DROP | MHASSAN | Approved | |
07/18/2019 | ELECTRIC - ABOVE CEILING | MHASSAN | Approved | ANY MISSING INSPECTIONS SHOULD BE UNDER THE TI PERMIT |
07/18/2019 | ELECTRIC - INTERMEDIATE | MHASSAN | Approved | FOR MISSING INSPECTIONS SEE TI AND FOUNDATION PERMITS |
07/18/2019 | ELECTRIC - UFER | MHASSAN | Approved | |
07/18/2019 | SHEET ROCK NAILING | MHASSAN | Approved | |
07/18/2019 | U VALUE FOR WINDOW | MHASSAN | Approved | |
07/18/2019 | BUILDING ABOVE CEILING | MHASSAN | Approved | THESE INSPECTIONS WERE UNDER TI PERMIT |
07/18/2019 | STUCCO MESH | MHASSAN | Approved | |
07/19/2019 | NPPO - FINAL | BBENEDON | Approved | |
07/19/2019 | SIGN - FINAL | BBENEDON | Approved | |
07/19/2019 | LANDSCAPE - FINAL | BBENEDON | Approved | |
07/19/2019 | FIRE SPKLR - FINAL | Bravin | Approved | No issues |
07/22/2019 | OUTDOOR LIGHTING FINAL | MHASSAN | Approved | |
07/22/2019 | MECHANICAL - FINAL | MHASSAN | Approved | |
07/22/2019 | FIREWALL/FIREBARRIER/FIRESTOP | MHASSAN | Approved | |
07/22/2019 | FRAMING | MHASSAN | Approved | |
07/22/2019 | EXT METAL CLIPS/EXT SHEATHING | MHASSAN | Approved | |
07/22/2019 | STEM WALL/RETAINING WALL | MHASSAN | Approved | |
10/29/2019 | ENGINEERING - FINAL | BBENEDON | Approved | Approved pending approval of the development package permit. I spoke with Jim asked him to schedule all of the remaining items And to provide the latest set of city approved plans |
10/18/2022 | ELECTRIC - FINAL | CTREVIL | Approved | |
10/18/2022 | BUILDING - FINAL | CTREVIL | Approved |