Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Address:
2246 E 7TH ST
Address NEW:
2246 E 7TH ST
Apply Date:
07/27/2018
Applicant:
Del Paules
Description:
DEMO ROOM ADD AND REMODEL*Variance T19SA00160 / C9-19-10 was approved for setback reductions. See

Permit Reviews

Permit Number - T18CM05839
Permit Status: Complete
Permit Description: DEMO ROOM ADD AND REMODEL*Variance T19SA00160 / C9-19-10 was approved for setback reductions. See
Start Date Submittal Complete Date Status  
05/29/2019 RESUBMITTAL 07/20/2020 COMPLETED Review Details
07/27/2018 PLANS OK TO SUBMIT - RES 12/03/2018 COMPLETED Review Details
08/26/2020 RESUBMITTAL 08/28/2020 COMPLETED Review Details
12/03/2018 RESUBMITTAL 05/29/2019 COMPLETED Review Details

Conditions

Permit Number - T18CM05839
Permit Status: Complete
Permit Description: DEMO ROOM ADD AND REMODEL*Variance T19SA00160 / C9-19-10 was approved for setback reductions. See
Date Description Comments
07/27/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Outstanding Inspections

Permit Status: Complete
Permit Number: T18CM05839
Permite Description: DEMO ROOM ADD AND REMODEL*Variance T19SA00160 / C9-19-10 was approved for setback reductions. See
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
10/27/2022 COT - LCPL - Plumbing Intermediate N/A Not Ready
10/26/2022 COT - RSBU - Excavation/Rebar/Zoning N/A Not Ready
10/26/2022 COT - RSBU - Stem Wall/Retaining Wall N/A Not Ready
10/26/2022 COT - RSEL - Grounding/Bonding N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: T18CM05839
Permit Description: DEMO ROOM ADD AND REMODEL*Variance T19SA00160 / C9-19-10 was approved for setback reductions. See
Total Completed Inspections - 22
Date Description Inspector Results Comments
07/09/2021 COT - RSPL - Rough Soil Passed {Activity date: 07/09/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by VLEON1 - APPROVED OK TO COVER PROGRESS AREAS} ; {Activity date: 06/29/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VLEON1 - Partial. Waste and vent lines in original house; 2”-4”. Ok to cover progress areas.}
07/14/2021 COT - RSBU - Preslab Passed {Activity date: 07/14/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by RSALDAT1 - AP}
11/04/2021 COT - RSPL - Yard Water Line Passed {Activity date: 11/04/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap}
12/08/2021 COT - RSBU - Roof Nailing Passed {Activity date: 12/08/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to dry in roof system.}
02/07/2022 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed {Activity date: 02/07/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Garage exterior walls. Ok to cover. Please reopen this inspection and include these results.

} ; {Activity date: 11/30/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved}
03/09/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 03/09/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - CODE TMPP}
03/09/2022 COT - RSEL - Construction Power Passed {Activity date: 03/09/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to energize temporary power.

CLEARANCE: Code: TMPP}
06/16/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 06/16/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/23/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready, contractor rescheduled}
06/16/2022 COT - LCBU - Framing Passed {Activity date: 06/16/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 02/07/2022; Status: Not ready for Inspection; Inspector: JBURGE; Comment: Entered by VVERA1 - Not ready. Contractor cancelled.}
06/16/2022 RSME - Mechanical Progress Passed {Activity date: 06/16/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved}
06/16/2022 COT - RSPL - Gas Pressure Test Passed {Activity date: 06/16/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved}
01/10/2023 COT - RSEL - Outdoor Lighting Passed
01/10/2023 COT - LCPL - Plumbing Intermediate Passed
01/10/2023 COT - RSEL - Electrical Underground Passed
01/03/2024 COT - RSME - Mechanical Final Passed Construction is complete. All mechanical, electrical, and plumbing fixtures are installed and working properly. Okay to issue certificate of completion or occupancy for this project.
01/03/2024 COT - RSEL - Electrical Final Passed Construction is complete. All mechanical, electrical, and plumbing fixtures are installed and working properly. Okay to issue certificate of completion or occupancy for this project.
01/03/2024 RSBU - Building Final Passed Construction is complete. All mechanical, electrical, and plumbing fixtures are installed and working properly. Okay to issue certificate of completion or occupancy for this project.
01/03/2024 COT - RSPL - Plumbing Final Passed Construction is complete. All mechanical, electrical, and plumbing fixtures are installed and working properly. Okay to issue certificate of completion or occupancy for this project.
01/03/2024 COT - BULD - SWG Clearance Passed gas line has been tested and approved. okay to install meter and turn on gas.
01/03/2024 COT - RSBU - Excavation/Rebar/Zoning Passed 1/3/2024: Footings are correct and complete.
01/03/2024 COT - RSBU - Stem Wall/Retaining Wall Passed 1/3/2024: Footings are correct and complete.
01/03/2024 COT - RSEL - Grounding/Bonding Passed

Documents

File Name Document Type  
1910TEFINAL.PDF DOCUMENTS VIEW
2246 E 7TH ST ARCHITECTURAL DOCUMENTATION.PDF DOCUMENTS VIEW