Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T18CM04912
Permit Details
Status:
L of c
Type:
COMMERCIAL ALTERATION
Address:
2801 N COUNTRY CLUB RD
Address NEW:
2801 N COUNTRY CLUB RD
Apply Date:
06/22/2018
Applicant:
CATALANO, VINCENT VICTOR
Description:
TI: MARKET
Architects:
- CATALANO, VINCENT VICTOR
Permit Reviews
Permit Number - T18CM04912
Permit Status: L of c
Permit Description: TI: MARKET
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/22/2018 | COMMERCIAL - TI | 06/25/2018 | COMPLETED |
| 06/25/2018 | COMMERCIAL - TI | 07/13/2018 | COMPLETED |
| 07/13/2018 | COMMERCIAL - TI | 07/23/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM04912
Permit Status: L of c
Permit Description: TI: MARKET
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/22/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T18CM04912
Permit Description: TI: MARKET
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/30/2018 | SITE - SEWER | DFLORES2 | Approved | |
| 07/30/2018 | PLUMBING - ROUGH, SOIL | DFLORES2 | Approved | |
| 08/17/2018 | MECHANICAL - HOODS | DFLORES2 | Approved | SMOKE TEST WAS CONDUCTED AND PASSED |
| 08/17/2018 | BUILDING ABOVE CEILING | DFLORES2 | Approved | |
| 08/17/2018 | FRAMING | DFLORES2 | Approved | |
| 10/22/2018 | MECHANICAL - ABOVE CEILING | MHASSAN | Approved | |
| 10/22/2018 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | |
| 10/22/2018 | PLUMBING - PROGRESS | MHASSAN | Approved | either put plug-in valves or connect to appliances |
| 10/22/2018 | PLUMBING - GAS PRESSURE TEST | MHASSAN | Approved | okay to clear gas for new service sent email into pdsd clearances |
| 10/22/2018 | PLUMBING - ABOVE CEILING | MHASSAN | Approved | |
| 10/22/2018 | PLUMBING - INTERMEDIATE | MHASSAN | Approved | |
| 10/22/2018 | ELECTRIC - ABOVE CEILING | MHASSAN | Approved | existing lighting or new lighting needs to meet requirements on page A4 under lighting intensity |
| 10/22/2018 | ELECTRIC - INTERMEDIATE | MHASSAN | Approved | |
| 10/23/2018 | GAS CLEARANCE | MHASSAN | Approved | |
| 11/06/2018 | FIRE - FINAL | gsereno1 | Approved | |
| 11/06/2018 | FIRE - KITCHEN EXH HOOD FINAL | gsereno1 | Approved | |
| 11/07/2018 | MECHANICAL - FINAL | JBURGE | Approved | |
| 11/07/2018 | PLUMBING - FINAL | JBURGE | Approved | |
| 11/07/2018 | ELECTRIC - FINAL | JBURGE | Approved | |
| 11/07/2018 | BUILDING - FINAL | JBURGE | Approved | |
| 11/07/2018 | HEALTH DEPT - FINAL 724-7908 | BBENEDON | Approved |