Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Apply Date:
06/11/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
EVENT AND OFFICE SPACE
Architects:
  • SAYLER-BROWN, THOMAS
Contractors:
  • CANYON BUILDING AND DESIGN LLC *APA*

Permit Reviews

Permit Number - T18CM04531
Permit Status: C of o
Permit Description: EVENT AND OFFICE SPACE
Start Date Submittal Complete Date Status  
06/11/2018 PLANS OK TO SUBMIT - COMM 06/11/2018 COMPLETED Review Details
06/19/2018 3RD PARTY REVIEW - COMMERCIAL 07/10/2018 COMPLETED Review Details
08/10/2018 3RD PARTY REVIEW - REVISION/OTHER 08/10/2018 ACTIVE Review Details

Outstanding Activity Conditions

Permit Number - T18CM04531
Permit Status: C of o
Permit Description: EVENT AND OFFICE SPACE
Total Outstanding Activity Conditions - 1
Date Name
06/11/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T18CM04531
Permit Description: EVENT AND OFFICE SPACE
Total Completed Inspections - 20
Date Description Inspector Results Comments
09/24/2018 BUILDING PRE-SLAB MRAMBER Approved
10/03/2018 PLUMBING - PRE SLAB MRAMBER Approved
10/12/2018 SHEET ROCK NAILING MRAMBER Approved
11/09/2018 MECHANICAL - INTERMEDIATE RCAMACHO Approved Storage room 519
Firestop behind north sink furrout ok to cover
11/14/2018 ELECTRIC - INTERMEDIATE MRAMBER Approved 5th floor ok to energize.
ECO ok to clear 5th floor hexigon
11/15/2018 PLUMBING - INTERMEDIATE MRAMBER Approved Toilet flanges ok
11/15/2018 TEP CLEARANCE - AM MRAMBER Approved ECO
12/05/2018 FIRE - FINAL JPEELDAVIS Approved
12/05/2018 FIRE - ALARM FINAL JPEELDAVIS Approved
12/05/2018 FIRE SPKLR - FINAL JPEELDAVIS Approved
12/05/2018 BUILDING ABOVE CEILING MRAMBER Approved
12/05/2018 PLUMBING - FINAL MRAMBER Approved Pending sterilization report approval.
12/05/2018 ELECTRIC - FINAL MRAMBER Approved
12/05/2018 BUILDING - FINAL MRAMBER Approved Pending all trades and inspections
12/06/2018 MECHANICAL - ABOVE CEILING MRAMBER Approved
12/06/2018 PLUMBING - ABOVE CEILING MRAMBER Approved
12/06/2018 ELECTRIC - ABOVE CEILING MRAMBER Approved
12/06/2018 FRAMING MRAMBER Approved
12/12/2018 MECHANICAL - FINAL RSHERRY Approved AIR BALANCE SHOWS FC-5.1 HAS NO OUTSID AIR AND EF-5.1 IS NOT MOVING THE SPECIFIED QUANTITY OF AIR.
06/13/2019 ELECTRIC - SERVICE UPGRADE qjones1 Approved approved per 2090

Documents

File Name Document Type  
T18CM04531 TEMP CERT OF OCC.PDF CERT OF OCC VIEW
None CERT OF OCC VIEW
T18CM04531 CERT OF OCC.PDF CERT OF OCC VIEW
None CERT OF OCC VIEW
001_G1.7.TIF CONSTRPLANS VIEW
002_A4.8.TIF CONSTRPLANS VIEW
003_A4.8.1.TIF CONSTRPLANS VIEW
004_A4.9.TIF CONSTRPLANS VIEW
005_A4.9.1.TIF CONSTRPLANS VIEW
006_A8.5.TIF CONSTRPLANS VIEW
007_A8.6.TIF CONSTRPLANS VIEW
008_A8.7.TIF CONSTRPLANS VIEW
009_A8.8.TIF CONSTRPLANS VIEW
010_A8.9.TIF CONSTRPLANS VIEW
011_M5.0.TIF CONSTRPLANS VIEW
012_M5.1.TIF CONSTRPLANS VIEW
013_M6.0.TIF CONSTRPLANS VIEW
014_M7.0.TIF CONSTRPLANS VIEW
015_M7.1.TIF CONSTRPLANS VIEW
016_M7.3.TIF CONSTRPLANS VIEW
017_P1.0.TIF CONSTRPLANS VIEW
018_P4.0.TIF CONSTRPLANS VIEW
019_P5.0.TIF CONSTRPLANS VIEW
020_P7.0.TIF CONSTRPLANS VIEW
021_E1.1.TIF CONSTRPLANS VIEW
022_E2.1.TIF CONSTRPLANS VIEW
023_E3.1.TIF CONSTRPLANS VIEW
024_E3.2.TIF CONSTRPLANS VIEW
025_E4.1.TIF CONSTRPLANS VIEW
026_E5.0.TIF CONSTRPLANS VIEW
027_E6.0.TIF CONSTRPLANS VIEW
028_E7.0.TIF CONSTRPLANS VIEW
None DOCUMENTS VIEW
T18CM04531 WATER REPORT.PDF DOCUMENTS VIEW
None DOCUMENTS VIEW